Traditional and Electronic Current Transformers Theory Testing Chapter | 10 121
FIGURE 10.19 Current transformer burden test.
10.9.2.7 Continuity of Secondary Circuits
The test should including checking of terminations, shorting links by the pri-
mary and secondary injection test.
10.9.2.8 High Voltage Test
This which is undertaken during the high-voltage test at the final stages of
commissioning tests, but with disconnecting the CT connections to the relays
and shorting the transformer secondaries during the high-voltage test.
10.9.2.9 Demagnetizing the CT Cores
Demagnetizing the CT cores by connecting the transformer’s secondaries to
the ground at the end of all tests.