Page 577 - Rock Mechanics For Underground Mining
P. 577

EXAMPLES OF MONITORING ROCK MASS PERFORMANCE























              Figure 18.11 Cross section through
              Racecourse orebodies at 6570N,
              Mount Isa mine, Australia, show-
              ing mining sequence in 13–11 level
              lift leading to formation of 11 level
              crown pillar (after Lawrence and
              Bock, 1982).

                                          The stability of the crown pillars is of major concern in this type of mining. A
                                        justifiable mining objective is to recover as much ore as possible from the pillars.
                                        However, men and machines work in the advancing stopes and their safety must be
                                        ensured. Potential hazards in the stopes are rock falls from the crown and buckling
                                        failures in the hanging- and footwalls. For the 11–9 level and 13–11 level lifts the
                                        stopes were advanced up-dip in a sequence that ensured that all stope backs were kept
                                        in a line perpendicular to bedding (Figure 18.11). This method was adopted to ensure
                                        that the major principal stress would always act normal to the bedding and so eliminate
                                        the possibility of crown instability being induced by slip on the bedding planes.
                                          At stage 3 of the 13–11 level lift (Figure 18.11) very high stresses developed in
                                        the stope crowns. This produced spalling of intact rock, rock falls, audible rock noise
                                        and rockbursts in the 11 level crown pillar above 7 and 8 orebodies. A series of stress
                                        measurements made at various locations on 11 level showed that the induced stresses
                                        were very high. At 6650N (Figure 18.12) a major principal stress of 95 MPa was
                                        measured perpendicular to the bedding.
                                          Because of the bad ground conditions in the crowns of the leading hangingwall
                                        stopes, mining in these stopes ceased, and further mining was undertaken in the foot-
                                        wall orebodies, which were ‘lagging’ behind under the mining strategy that was being
                                        used. It was noted that, where this was done, shear displacement occurred on a few
                                        bedding planes in the crown pillars of the hangingwall orebodies and ground condi-
                                        tions improved. Figure 18.12 shows the shear displacements measured in such a case
                                        at 6650 N between December 1975, when the high stresses previously referred to were
                                        measured on 11 level, and December 1977, when much lower stresses were measured.
                                          The mechanical explanation of this destressing phenomenon is that, by advancing
                                        the footwall stopes, the principal stress directions in the crown pillar became inclined
                                        to the bedding planes. Because of the very low shear strengths of the bedding planes
                                        559
   572   573   574   575   576   577   578   579   580   581   582