11 - PROJECT RISK MANAGEMENT







                                                              Project Risk
                                                          Management Overview


                                  11.1 Plan Risk            11.2 Identify Risks      11.3 Perform Qualitative
                                   Management                                             Risk Analysis
                              .1 Inputs                  .1 Inputs                   .1 Inputs
                                .1 Project management plan    .1 Risk management plan    .1 Risk management plan
                                .2 Project charter         .2 Cost management plan     .2 Scope baseline
                                .3 Stakeholder register    .3 Schedule management plan    .3 Risk register
                                .4 Enterprise environmental      .4 Quality management plan    .4 Enterprise environmental
                                 factors                   .5 Human resource management       factors
                                .5 Organizational process assets     plan              .5 Organizational process assets
                                                           .6 Scope baseline
                              .2 Tools & Techniques        .7 Activity cost estimates  .2 Tools & Techniques
                                .1 Analytical techniques    .8 Activity duration estimates    .1 Risk probability and impact
                                .2 Expert judgment         .9 Stakeholder register      assessment
                                .3 Meetings                .10 Project documents       .2 Probability and impact matrix
                                .4 Additional considerations    .11 Procurement documents    .3 Risk data quality assessment
                                                           .12 Enterprise environmental      .4 Risk categorization
                              .3 Outputs                    factors                    .5 Risk urgency assessment
                                .1 Risk management plan    .13 Organizational process assets    .6 Expert judgment
                                                           .14 Risk taxonomies         .7 Additional considerations
                                                         .2 Tools & Techniques       .3 Outputs
                             11.4 Perform Quantitative     .1 Documentation reviews    .1 Project documents updates       11
                                                           .2 Information gathering
                                  Risk Analysis             techniques
                                                           .3 Checklist analysis
                              .1 Inputs                    .4 Assumptions analysis
                                .1 Risk management plan    .5 Diagramming techniques    11.6 Control Risks
                                .2 Cost management plan    .6 SWOT analysis
                                .3 Schedule management plan    .7 Expert judgment
                                .4 Risk register           .8 Retrospective meetings  .1 Inputs
                                .5 Enterprise environmental                            .1 Project management plan
                                 factors                 . 3 Outputs                   .2 Risk register
                                .6 Organizational process assets    .1 Risk register    .3 Work performance data
                                                                                       .4 Work performance reports
                              .2 Tools & Techniques
                                .1 Data gathering and                                .2 Tools & Techniques
                                 representation techniques                             .1 Risk reassessment
                                .2 Quantitative risk analysis and                      .2 Risk audits
                                 modeling techniques     11.5 Plan Risk Responses      .3 Variance and trend analysis
                                .3 Expert judgment                                     .4 Technical performance
                                                         .1 Inputs                      measurement
                              .3 Outputs                   .1 Risk management plan       .5 Reserve analysis
                                .1 Project documents updates    .2 Risk register       .6 Meetings
                                                         .2 Tools & Techniques       .3 Outputs
                                                           .1 Strategies for negative risks or    .1 Work performance information
                                                            threats                    .2 Change requests
                                                           .2 Strategies for positive risks or    .3 Project management plan
                                                            opportunities               updates
                                                           .3 Contingent response      .4 Project documents updates
                                                            strategies                 .5 Organizational process assets
                                                           .4 Expert judgment           updates
                                                           .5 Additional considerations
                                                         .3 Outputs
                                                           .1 Project management plan
                                                            updates
                                                           .2 Project documents updates
                                                           .3 Additional considerations

                                         Figure 11-1. Software Project Risk Management Overview