ChaPter 3  •  ProjeCt management     73



                                                  CONSULTING OPPORTUNITY 3.4



                                                           Food for Thought



                    “We could really make some changes. Shake up some peo-    A week later, Kim enters Malcolm’s office with several
                    ple. Let them know we’re with it. Technologically, I mean,” said   pages of interview notes in hand. “I’ve talked with most of the
                    Malcolm Warner, vice president for AllFine Foods, a wholesale   people who have extensive contact with the system. They’re
                    dairy products distributor. “That old system should be overhauled.   happy, Malcolm. And they’re not just talking through their
                    I think we should just tell the staff that it’s time to change.”  hats. They know what they’re doing.”
                       “Yes, but what would we actually be improving?” Kim Han,   “I’m sure the managers would like to have a newer system
                    assistant to the vice president, asks. “I mean, there aren’t any sub-  than the guys at Quality Foods,” Malcolm replies. “Did you
                    stantial problems with the system input or output that I can see.”  talk to them?”
                       Malcolm snaps, “Kim, you’re purposely not seeing my    Kim says, “Yes. They’re satisfied.”
                    point. People out there see us as a stodgy firm. A new computer   “And how about the people in systems? Did they say
                    system could help change that. Change the look of our invoices.   the technology to update our system is out there?” Malcolm
                    Send jazzier reports to the food store owners. Get some people   inquires insistently.
                    excited about us as leaders in wholesale food distributing and   “Yes. It can be done. That doesn’t mean it should be,”
                    computers.”                                            Kim says firmly.
                       “Well, from what I’ve seen over the years,” Kim replies   As the systems analyst for AllFine Foods, how would
                    evenly, “a new system is very disruptive, even when the business   you assess the feasibility of the systems project Malcolm is
                    really needs it. People dislike change, and if the system is perform-  proposing? Based on what Kim has said about the managers,
                    ing the way it should, maybe there are other things we could do to   users, and systems people, what seems to be the operational
                    update our image that wouldn’t drive everyone nuts in the process.   feasibility of the proposed project? What about the economic
                    Besides, you’re talking big bucks for a new gimmick.”  feasibility? What about the technological feasibility? Based
                       Malcolm  says,  “I  don’t think just tossing  it around  here   on what Kim and Malcolm have discussed, would you recom-
                    between the two of us is going to solve anything. Check on it and   mend that a full-blown systems study be done? Discuss your
                    get back to me. Wouldn’t it be wonderful?”             answer in a paragraph.



                     The systems analyst, of course, has the option to break down steps further. For instance,
                 the analyst could specify each of the persons to be interviewed. The amount of detail necessary
                 depends on the project, but all critical steps need to appear in the plans.
                     Sometimes the most difficult part of project planning is the crucial step of estimating the
                 time it takes to complete each task or activity. When quizzed about reasons for lateness on a par-
                 ticular project, project team members cited poor scheduling estimates that hampered the success


                                                                                                Figure 3.17
                                                                                Weeks
                       Activity                   Detailed Activity             Required        Refining the planning and
                                                                                                scheduling of analysis activities
                       Data gathering             Conduct interviews               3            by adding detailed tasks and
                                                  Administer questionnaires        4            establishing the time required to
                                                  Read company reports             4            complete the tasks.
                                                  Introduce prototype              5
                                                  Observe reactions to prototype   3

                       Data flow and decision analysis  Analyze data flow          8
                       Proposal preparation       Perform cost-benefit analysis    3
                                                  Prepare proposal                 2
                                                  Present proposal                 2
                                                               then estimate
                                                               time required.
                                     Break  these
                                    down further,