Page 102 -
P. 102

ChaPter 3  •  ProjeCt management     69


                                                                           Year
                                                1          2          3           4          5          6          Total

                  Costs                      $40,000     42,000     44,100     46,300      48,600     51,000
                  Multiplier                     .89        .80        .71        .64         .57        .51
                  Present Value of Costs      35,600     33,600     31,311     29,632      27,702     26,010     183,855

                  Benefits                   $25,000     31,200     39,000     48,700      60,800     76,000
                  Multiplier                     .89        .80        .71        .64         .57        .51
                  Present Value of Benefits   22,250     24,960     27,690     31,168      34,656     38,760     179,484

                 Figure 3.14
                 Taking into account present value, the conclusion is that the costs are greater than the benefits. In calculating
                 the multipliers in this table, the discount rate, i, is assumed to be .12.

                     For instance, a $1 investment at 7 percent today will be worth $1.07 at the end of the year
                 and will double in approximately 10 years. The present value, therefore, is the cost or benefit
                 measured in today’s dollars and depends on the cost of money. The cost of money is the oppor-
                 tunity cost, or the rate that could be obtained if the money invested in the proposed system were
                 invested in another (relatively safe) project.
                     The present value of $1 at a discount rate of i is calculated by determining the factor:

                                                       1

                                                     11 1 i2 n
                 where n is the number of periods. Then the factor is multiplied by the dollar amount, yielding the
                 present value, as shown in Figure 3.14. In this example, the cost of money—the discount rate—
                 is assumed to be .12 (12 percent) for the entire planning horizon. Multipliers are calculated for
                 each period: n = 1, n = 2, . . . , n = 6. Present values of both costs and benefits are then calculated
                 using these multipliers. When this step is done, the total benefits (measured in today’s dollars)
                 are $179,484 and are thus less than the costs (also measured in today’s dollars). The conclusion
                 to be drawn is that the proposed system is not worthwhile if present value is considered.
                     Although this example, which uses present value factors, is useful in explaining the concept,
                 all electronic spreadsheets have a built-in present value function. An analyst can directly com-
                 pute present value by using this function.
                 GUIDELINES FOR ANALYSIS.  The use of the methods discussed in the preceding subsections
                 depends on the methods employed and accepted in the organization. For general guidelines,
                 however, it is safe to say the following:

                   1. Use break-even analysis if the project needs to be justified in terms of cost, not benefits, or
                     if benefits do not substantially improve with the proposed system.
                   2. Use payback when the improved tangible benefits form a convincing argument for the pro-
                     posed system.
                   3. Use cash-flow analysis when the project is expensive relative to the size of the company or
                     when the business would be significantly affected by a large drain (even if temporary) on funds.
                   4. Use present value analysis when the payback period is long or when the cost of borrowing
                     money is high.
                 Whichever method is chosen, it is important to remember that cost-benefit analysis should be
                 approached systematically, in a way that can be explained and justified to managers, who will
                 eventually decide whether to commit resources to the systems project. Next, we turn to the
                 importance of comparing many systems alternatives.


                 Managing Time and Activities
                 The process of analysis and design can become unwieldy, especially when the system being
                 developed is large. To keep the development activities as manageable as possible, you usually
                 use some of the techniques of project management to help get organized.
   97   98   99   100   101   102   103   104   105   106   107