18 Cha pte r O n e
Possible Tentative
Yes ? No Points Points
EAc3: Enhanced Commissioning 2
EAc4: Enhanced Refrigerant Management 2
EAc5: Measurement and Verification 3
EAc6: Green Power (35% - 2 years) 2
Y MRp1: Storage & Collection of Recyclables Required −
MRc1.1: Building Reuse-Maintain Existing Walls, 1–3
Floors & Roof
[1 pt-55%; 2 pts-75%; 3 pts-95%]
MRc1.2: Building Reuse-Maintain Existing Interior 1
Nonstructural Elements
MRc2: Construction Waste Management 1–2
[1 pt-50%; 2 pts-75%]
MRc3: Materials Reuse 1–2
[1 pt-5%; 2 pts-10%]
MRc4: Recycled Content 1–2
[1 pt-10%; 2 pts-20%]
MRc5: Regional Materials 1–2
[1 pt-10%; 2 pts-20%]
MRc6: Rapidly Renewable Materials 1
MRc7: Certified Wood 1
Y IEQp1: Minimum Indoor Air Quality Performance Required −
Y IEQp2: Environmental Tobacco Smoke (ETS) Control Required −
IEQc1: Outdoor Air Delivery Monitoring 1
IEQc2: Increased Ventilation 1
IEQc3.1: Construction IAQ Management Plan, during 1
Construction
IEQc3.2: Construction IAQ Management Plan, before 1
Occupancy
IEQc4.1: Low-Emitting Materials, Adhesives and 1
Sealants
IEQc4.2: Low-Emitting Materials, Paints and Coatings 1
IEQc4.3: Low-Emitting Materials, Flooring Systems 1
IEQc4.4: Low-Emitting Materials, Composite Wood 1
and Agrifiber Products
IEQc5: Indoor Chemical and Pollutant Source Control 1
IEQc6.1: Controllability of Systems Lighting 1
IEQc6.2: Controllability of Systems Thermal Comfort 1
TABLE 1.2.4 Blank Example LEED 2009 Checklist for Columbia, SC 29201 (Sheet 2) (Continued)