Page 110 - The Handbook for Quality Management a Complete Guide to Operational Excellence
P. 110

96   I n t e g r a t e d   P l a n n i n g                                   S t r a t e g i c   P l a n n i n g    97




                               Critical path
                               - Uncorrected for resource availability
                               - Note the contention for use of resource 3
                               - Project schedule indicates finish in 67 days
                               - Actual finish date will be much later (85+ days)
                                         Resource-4   Resource-3  Resource-5
                        P1 A
                                                                  Critical path
                          B
                               Resource-1  Resource-2
                                          Resource-1  Resource-3
                          C
                            0 1 2 3 4 5 6 7 8 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49 51 53 55 57 59 61 63 65 67 69 71 73 75 77 79 81 83 85 87 89 91 93 95


                               Critical chain
                               - Resource contention eliminated
                               - Protective “pad” removed from each activity
                               - Project buffer added
                               - Planned completion: 68 days
                                   Resource-4  Resource-3  Resource-5
                        P1 A                                   Project buffer
                                                        Critical chain
                          B
                             Resource-1  Resource-2
                                         Resource-1  Resource-3
                          C
                            0 1 2 3 4 5 6 7 8 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49 51 53 55 57 59 61 63 65 67 69 71 73 75 77 79 81 83 85 87 89 91 93 95

                              Effect of critical chain project management (actual status)
                              - Task durations vary (some take longer, some take less time)
                              - Double-line arrows indicate actual activity start and finish
                              - Project actually completes in 55 days (versus 68 days planned)
                                                                  Actual
                                                                          Planned
                        P1 A


                          B

                          C
                            0 1 2 3 4 5 6 7 8 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49 51 53 55 57 59 61 63 65 67 69 71 73 75 77 79 81 83 85 87 89 91 93 95
                      Figure 5.10  Critical Chain versus Critical Path.



                                      irrelevant. What results is a dif ferent time duration, based on resource
                                      usage.  This  is  the  Critical  Chain.  (Refer  to  Fig.  5.10.)  Because  the
                                      Critical Chain now constitutes the con straint that determines the
                                      earliest date that a project can finish, it’s cru cial to monitor progress
                                      along the Critical Chain, because it reflects the progress of the entire
                                      project.








          05_Pyzdek_Ch05_p061-102.indd   97                                                             11/9/12   5:04 PM
   105   106   107   108   109   110   111   112   113   114   115