Page 111 - Urban Construction Project Management
P. 111

70    Chapter Four
         Exhibit 4-6         Contractor  Item No.  Activity                     Target Date Actual Completion
                             Electrical  1  Permanent Power
         TCO requirement.                    a.  Utility will have vault completed by
                                             b.  Electrical contractor will require 5 days to sequence the installation
                                              of permanent power to the building from the time the power company
                                             brings power to the building.
                                             c.  Removing all temporary power
                                        2  Wiring of smoke fans
                                        3  Testing rotation of all fans and pumps with permanent power
                                        4  City electrical inspections ongoing
                                        5  All mechanical dampers completely wired to fire alarm system
                                        6  Fire alarm
                                             a.  Complete fire alarm system installation including in-house test
                                             b.  Fire alarm shall include the following:
                                                   1.  Smoke detectors
                                                   2.  Heat detectors
                                                   3.  Pull stations
                                                   4.  Apartment smoke detectors
                                                   5.  Speaker/strobes
                                                   6.  Dust detectors
                                                   7.  Fire alarm panel and remote enunciator
                                                   8.  Interface with:
                                                           -elevators
                                                           -generator
                                                           -fire pump
                                                           -smoke control
                                                    9.  Recall alternate
                                                  10.  Connection to sprinkler flow and tamper switches
                                                  11.  Firefighters’ communication
                                                  12.  One-way communication
                                                  13.  In-house test
                                        7  Fire alarm testing by city to begin
                                        8  Fire alarm city testing completed by
                                        9  Emergency Power including in-house generator test with loads and load
                                           bank to be completed by
                                             a.  Emergency power to include the following:
                                                    1.  Life safety systems
                                                    2.  Smoke control fans
                                                    3.  Stair pressurization
                                                    4.  Smoke control panel
                                                    5.  Wire and supervision
                                                    6.  Fire dampers
                                                    7.  Elevator shaft pressurization
                                                    8.  Garage smoke purge
                                                    9.  Emergency lighting
                                                  10.  Stair and exit lighting
                                                  11.  One elevator per bank
                                                  12.  Exit signs
                                                  13.  Emergency lighting
                                       10  City emergency test (TCO)


                            the architectural integrity of the district. The federal government also has guidelines for
                            the preservation of historical buildings.

                            If you are working in a landmarks building or in a landmarks district, then additional
                            permit requirements need to be satisfied. In most cases, the professional architects and
                            engineers have to submit drawings to the Landmarks Commission and  Arts
                            Commission and possibly to the local community board for approvals. This process can
                            take from months to, in some cases, years to obtain the required approvals. In most
                            cases, construction permits cannot be obtained until the Landmarks Commission or
                            Federal Government has approved the scope of work proposed.
   106   107   108   109   110   111   112   113   114   115   116