Building Codes and Permits  71

           Contractor  Item No.  Activity                     Target Date Actual Completion  Exhibit 4-6
           HVAC      1   Smoke fans less duct work installed
                                                                                   (Continued)
                     2   Smoke fans including all duct work and controls including cleaning of
                         duct work complete
                     3   Stair pressurization including duct work and grills installation complete
                     4   Common area smoke fans including duct work and cleaning of duct work
                         complete
                     5   All dampers installation complete
                     6   Elevator shaft pressurization installation complete
                     7   Duct work for elevator shaft pressurization complete
                     8   City inspection of mechanical system complete
                     9   In-house test of smoke evacuation system under normal permanent power
                         including the following:
                           a.  Common areas
                           b.  Stair pressurization
                           c.  Elevator shaft pressurization
                           d.  Dampers
                           e.  Interface with fire alarm
                     10  Checking rotation and wiring of all fan systems with electrical contractor
                         complete
                     11  Engineer of record smoke bomb placement drawing
                     12  All grills and diffusers installation complete
                     13  City smoke test
           Plumbing  1   Incoming water service
                     2   Back flow preventer
                     3   Tags on all valves
                     4   All condo floors have been inspected by city
                     5   8" and 2" backflow preventers were installed
           Fire protection  1  Installation of taper and flow switches
                     2   Tower risers including manifolds
                     3   Loft risers including manifolds
                     4   Fire pumps
                     5   Jockey pumps
                     6   City inspection of fire pumps
                     7   Sprinkler installation
                     8   Backflow preventer
                     9   Ground floor sprinkler








          The responsibility of the CM/GC usually involves the submittal of material that will be
          used for the landmarks project. The Landmarks Commission wants to make sure that
          the specified material (as agreed to by the Landmarks Commission) and the actual
          material are consistent with the intent of the architecture approved. The CM/GC should
          be aware of potential time delays in obtaining the necessary approvals for materials and
          their finishes.