Exhibit 6-5
Item Details Requirements
Logistics checklist.
Logistics
Logistics plan Plan of total area
Hours of operation Hours that the site will be open
and any municipal restrictions
Transportation stops Bus, subway, and tram stops must
be evaluated
Moratorium periods Restricted days when construction
activitity has to be curtailed
Field office and shanties For CM/GC/Subcontractors/Owner/Consultants.
Location of offices and shanties relative to site
entrance
Field office Administrative offices
Consultant’s office Offices for the architects and engineers
Sidewalk protection Safety for pedestrians
Shanties Subcontractors office and storage
Storage areas Location for storing large pieces of
equipment
Container Storage Storage for containers for demo
truck pick up
Special yards For the on-site fabrication of materials
and staging of equipment
Cylinder storage Acetylene torch and concrete
cylinders
Storage of flammable and
hazardous materials
Office power supply Power for field office and shanties
Loading dock Off load of equipment and material
Off-site storage To be considered because of
limitations on site space
First aid office Location for assisting injured workers
Temporary toilets Toilets for the workers
Location of temporary bathrooms
Heaters and A/C for construction
shanties
Utilities Telephone, fax, Internet service for
CM and trades
Utilizing permanent systems for use
during construction
Safety & Site Prep
Safety nets Nets required for safety of workers
and to catch any falling objects
Site security Security of site and offices
(Continued)