Page 168 - Urban Construction Project Management
P. 168
Logistics 123
Exhibit 6-5
Item Details Requirements
(Continued)
Water Siamese connection to feed stand pipe
Roofing Temporary roof
HVAC Temporary heat
Interim cooling and dehumidification
Security Protection of facilities
Maintenance
(General) Maintenance of temporary systems
Work that may affect the Transit
Authority work and zone of influence
Maintenance of temporaty facilities
and standby operating personnel
Of permanent facilities used during
the construction process
Refurbishment of equipment and
extension of all guarantees and
warranties
Fire Protection
(General) Fire resistant construction
Sprinkler protection of shanty areas
Stand pipe Fire department requirement
Fire extinguishers
Siamese connection Location for fire truck connection
Access to fire hydrants
Signage & Traffic
(General) Contractor’s name and emergency
numbers
Authorities Department of Buildings contact
information
Demolition Demolition subcontractor’s name and
emergency numbers
Interim use of building loading dock
Detours Pedestrians directional
Sidewalk closing
Lane closing
Direction of the flow of traffic
Bus lanes and stops
Subway entrances and exits
Visibility of traffic signage or
relocation of same
(Continued)