Page 222 - Urban Construction Project Management
P. 222

Drawings and Specifications

          8 (The 100% documents. Not!)
















          DRAWINGS AND SPECIFICATIONS



          Drawings and specifications represent the scope of the project and the details required
          for its construction. These documents will include plans, elevations, sections, reflected
          ceiling plans, blow-ups, definitive information (such as the type of pipe to use), and
          testing and quality control (QC) that will be used for the project. See Exhibit 8-1 for a
          drawings and specifications flowchart.
          The architects and associated consultants (design team) prepare the construction docu-
          ments. The construction documents are supposed to be coordinated by the design team
          that is involved with their preparation. The coordination process entails the review of
          the architectural, structural, mechanical, electrical, plumbing, sprinkler, and other plans
          to make sure conflicts do not occur between the various design team discipline draw-
          ings. Unfortunately, the reality of the consultant’s world is that the consultants usually
          do not have the proper time to coordinate and check the construction documents.
          Sometimes the owner who wants to begin construction immediately dictates this. Thus,
          the reality of the preparation of construction documents is that it is very rare that the
          construction manager/general contractor (CM/GC) will receive 100% completed
          documents.
          The CM/GC must review the documents for constructability. This is not to say that all
          discrepancies will be picked up. However, the CM/GC is trying to minimize potential
          problems.
          One of the first things the CM/GC wants to do is to make sure the latest construction
          documents have been submitted. This is achieved by requesting from the design team
          a list of all the construction documents indicating the latest revision dates. The design
          team’s list should also include all addendums, sketches, bulletins, specifications, and all
          other documents relevant to the construction of the project. Exhibit 8-2 is a design
          document log that should be kept by the project manager (PM).

                                                                                                 177
   217   218   219   220   221   222   223   224   225   226   227