Page 324 -
P. 324

UK Government         Case Study 7   323
                                                                                (Department of Health)



                                                                                       NHS



                                                           North           South      London             Midlands and East

                                                      X-rays sharing system (PAC), Electronic patient record system  (per regions North, South, ...)

                                                                                      Trusts,
                                                                               Community Health Services,
                                                                                 General Practices, ...




                    Figure 7-23                                              Patients, Healthcare Professionals
                    NPfIT Interorganizational IS






                    preceded  the NPfIT. This system was added  to  the NPfIT well   EAI - been undertaken from  the start of  the  project Although
                    after the original specifications were approved, following a meet-  praise-worthy in its ambition, the programme was motivated by
                    ing between NPfIT and health professionals.”          government in a  top-down fashion without fully consulting IT
                       By 2007, the system had been successfully rolled out and   experts, who would have been able to bring their project man-
                    delivered to all parts of the NHS organization with full buy-in   agement skills and experience to bear. The lack of involvement
                    with respect of all stakeholders,  with  their requirements in   of health professionals was found to be a major impediment as
                    respect of the system being fully met clinically as well as orga-  once systems and  processes were being evaluated,  there was a
                    nizationally. In these respects, the X-ray sharing system was an   lack of buy-in from these end-users. Also, the speed with which
                    exemplar for other projects and systems within the NPfIT.  contracts were awarded for the development of the system meant
                                                                          that planning, scope and deliverables among other crucial project
                    Electronic Patient Record System                      parameters fell seriously short. Having many contactors develop
                                                                          the system for different parts of the NHS organization meant that,
                    The Electronic Patient Record System, on the other hand,  was   in-theory, if any one contractor failed to deliver at any point in
                    still far from completion by 2011 when the NAO reported on its   the programme, they could be substituted with another. However,
                    progress in that year, some four years after the implementation   in  hindsight, this  multi-sourcing  approach proved to  be  near
                    of the X-rays sharing system.  According to estimates given then,     impossible to operate effectively, moving too far away from the
                    the work would have required a substantial further investment   tried-and-tested ‘one customer, one service  provider’ model of
                    and would not have been complete until 2015–2016. Even after   delivery.
                    reducing the functional specification so as to bring forward the   Any one of these factors may have been recoverable if iden-
                    delivery of the system at reduced cost to the NHS organization, it   tified in reasonable  time  during  the original  project schedule.
                    became evident that timescales and cost savings would have been   Unfortunately, this wasn’t the case and when taken together, the
                    largely unaffected. By the time of the report, the Department of   seeds of the programme’s failure were sown at an early stage.
                    Health, and ultimately the government decided to dismantle and
                    effectively cancel the programme in its NPfIT form.   QUeStionS
                       Since the cancellation of the project, a forensic examination
                    of the causes of the budget and time over-runs has taken place     7-11.  Summarize the purpose  and  intended benefits  of the
                    and the consensus is that at least four factors contributed to the   NHS Programme for IT patient record system.
                    abject failure of  the  programme:  motives,  buy-in,  haste, and     7-12.  Explain why the NHS Programme for IT patient record
                    multi-sourcing. These  could have been mitigated against had an   system requires an interorganizational information
                    interorganizational information system development – ERP, CRM,   system.
   319   320   321   322   323   324   325   326   327   328   329