Page 115 - Fluid Power Engineering
P. 115

W i nd Measurement    93


              correlation of the measured data with concurrent long-term dataset.
              If this correlation is low and the project economics is borderline, then
              there is no option but to continue measurement for 2 –3 years. Even if
              theprojecteconomicsisfavorable,butthedegreeofuncertaintyishigh
              because of measurement for shorter duration, investors may perceive
              the project as high risk and, therefore, demand a higher return. Longer
              measurement period will reduce the degree of uncertainty associated
              with wind speed and, thus reduce project risk. For large wind farms,
              it is normal for financiers to demand 2–3 years of met-tower data.


        Installation of Met-Towers
              Detailed guidelines for installing met-towers are available in the doc-
              umentation supplied by the vendor of the met-tower. Proper planning
              and appropriate safety precautions can mitigate the risk of cost over-
              runs and failures. Before installing a met-tower, the following should
              be done:

                    Examine the wind rose at the location. This will describe the pre-

                    dominant direction of wind and, therefore, is the primary in-
                    put into orienting the instruments on the tower.
                    Understand the terrain. Ensure that there is sufficient lay down

                    area to assemble the tower. For example, a 60-m tower may
                    need a lay down area of at least 80 m × 6 m, if the wind
                    direction is consistent.
                    Procure gin pole and winch. The winch must have the right size

                    drum that can hold sufficient length of wire. For example, a
                    60-m tower will need about 100 m of wire on the winch drum.
                    A crew size of four or more personnel, or as specified by the

                    tower vendor, is required to erect the tower.
                    Obtain local permits for the type of met-tower that is being

                    installed. Check the soil conditions and procure the right type
                    of anchors for the guy wires. Some states require Rev-G tow-
                    ers, which means procuring the right kind of tower and base.
                    In some situations, a concrete foundation for the tower may
                    be needed.
                    Procure and install proper electrical grounding rods.

                    Check the weather conditions, specifically rain and wind, be-

                    fore scheduling an install. Met-towers cannot be installed in
                    moderate to high winds and during thunderstorms.
                    Plan the orientation of instruments based on “Placement of

                    Sensors” section. In addition, ensure that guy wires do not
                    disturb the airflow over the instruments.
                    Program the data logger and communication equipment and

                    prepare documentation and forms before going to site.
   110   111   112   113   114   115   116   117   118   119   120