6 - PROJECT TIME MANAGEMENT






                      6.5.3 Estimate Activity durations: outputs



                      6.5.3.1 Activity duration Estimates

                         Activity duration estimates are quantitative assessments of the likely number of time periods that are required
                      to complete an activity. Duration estimates do not include any lags as described in Section 6.3.2.3. Activity duration
                      estimates may include some indication of the range of possible results. For example:

                            •   2 weeks ± 2 days, which indicates that the activity will take at least eight days and not more than twelve
                              (assuming a five-day workweek); and

                            •   15 % probability of exceeding three weeks, which indicates a high probability—85 %—that the activity
                              will take three weeks or less.


                      6.5.3.2 Project documents updates

                         Project documents that may be updated include, but are not limited to:

                           •  Activity attributes; and

                           •   Assumptions made in developing the activity duration estimate, such as skill levels and availability,
                              as well as a basis of estimates for durations.


                      6.6 develop Schedule


                         Develop Schedule  is  the  process  of  analyzing  activity  sequences,  durations,  resource  requirements, and
                      schedule constraints to create the project schedule model. The key benefit of this process is that by entering
                      schedule activities, durations, resources, resource availabilities, and logical relationships into the scheduling tool, it
                      generates a schedule model with planned dates for completing project activities. The inputs, tools and techniques,
                      and outputs of this process are depicted in Figure 6-16. Figure 6-17 depicts the data flow diagram of the process.




























             172      ©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK  Guide) – Fifth Edition
                                                                                          ®


                                           Licensed To: Jorge Diego Fuentes Sanchez PMI MemberID: 2399412
                                       This copy is a PMI Member benefit, not for distribution, sale, or reproduction.
   193   194   195   196   197   198   199   200   201   202   203