Page 200 -
P. 200

6 - PROJECT TIME MANAGEMENT






                         Developing an acceptable project schedule is often an iterative process.  The schedule model is used to
                      determine the planned start and finish dates for project activities and milestones based on the accuracy of the
                      inputs. Schedule development can require the review and revision of duration estimates and resource estimates to
                      create the project schedule model to establish an approved project schedule that can serve as a baseline to track
                      progress. Once the activity start and finish dates have been determined, it is common to have project staff assigned
                      to the activities review their assigned activities and confirm that the start and finish dates present no conflict with
                      resource calendars or assigned activities in other projects or tasks and thus are still valid. As work progresses,
                      revising and maintaining the project schedule model to sustain a realistic schedule continues throughout the
                      duration of the project, as described in Section 6.7.

                         For more specific information regarding scheduling, refer to the Practice Standard for Scheduling.



                      6.6.1 develop Schedule: Inputs


                      6.6.1.1 Schedule Management Plan


                         Described in Section 6.1.3.1. The schedule management plan identifies the scheduling method and tool used to
                      create the schedule, and how the schedule is to be calculated.


                      6.6.1.2 Activity List

                         Described in Section 6.2.3.1. The activity list identifies the activities that will be included in the schedule model.


                      6.6.1.3 Activity Attributes

                         Described in Section 6.2.3.2. The activity attributes provide the details used to build the schedule model.


                      6.6.1.4 Project Schedule network diagrams


                         Described in Section 6.3.3.1. The project schedule network diagrams contain the logical relationships of
                      predecessors and successors that will be used to calculate the schedule.





















             174      ©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK  Guide) – Fifth Edition
                                                                                          ®


                                           Licensed To: Jorge Diego Fuentes Sanchez PMI MemberID: 2399412
                                       This copy is a PMI Member benefit, not for distribution, sale, or reproduction.
   195   196   197   198   199   200   201   202   203   204   205