Page 202 -
P. 202

6 - PROJECT TIME MANAGEMENT






                      6.6.1.12 Enterprise Environmental Factors

                         Described in Section 2.1.5. The enterprise environmental factors include, but are not limited to:

                           •  Standards,
                           •  Communication channels, and

                           •  Scheduling tool to be used in developing the schedule model.


                      6.6.1.13 organizational Process Assets

                         Described in Section 2.1.4. The organizational process assets that can influence the Develop Schedule process
                      include, but are not limited to: scheduling methodology and project calendar(s).



                      6.6.2 develop Schedule: tools and techniques


                      6.6.2.1 Schedule network Analysis

                         Schedule network analysis is a technique that generates the project schedule model. It employs various analytical
                      techniques, such as critical path method, critical chain method, what-if analysis, and resource optimization
                      techniques to calculate the early and late start and finish dates for the uncompleted portions of project activities.
                      Some network paths may have points of path convergence or path divergence that can be identified and used in
                      schedule compression analysis or other analyses.


                      6.6.2.2 critical Path Method

                         The critical path method, which is a method used to estimate the minimum project duration and determine the
                      amount of scheduling flexibility on the logical network paths within the schedule model. This schedule network
                      analysis technique calculates the early start, early finish, late start, and late finish dates for all activities without
                      regard for any resource limitations by performing a forward and backward pass analysis through the schedule
                      network, as shown in Figure 6-18. In this example the longest path includes activities A, C, and D, and, therefore, the
                      sequence of A-C-D is the critical path. The critical path is the sequence of activities that represents the longest path
                      through a project, which determines the shortest possible project duration. The resulting early and late start and
                      finish dates are not necessarily the project schedule, rather they indicate the time periods within which the activity
                      could be executed, using the parameters entered in the schedule model for activity durations, logical relationships,
                      leads, lags, and other known constraints. The critical path method is used to calculate the amount of scheduling
                      flexibility on the logical network paths within the schedule model.












             176      ©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK  Guide) – Fifth Edition
                                                                                          ®


                                           Licensed To: Jorge Diego Fuentes Sanchez PMI MemberID: 2399412
                                       This copy is a PMI Member benefit, not for distribution, sale, or reproduction.
   197   198   199   200   201   202   203   204   205   206   207