Page 197 -
P. 197

6 - PROJECT TIME MANAGEMENT






                     Depending on the assumed distribution of values within the range of the three estimates the expected duration,
                   tE, can be calculated using a formula. Two commonly used formulas are triangular and beta distributions. The
                   formulas are:
                        •  triangular distribution. tE = (tO + tM + tP) / 3

                        •  Beta distribution (from the traditional PERT technique). tE = (tO + 4tM + tP) / 6
                     Duration estimates based on three points with an assumed distribution provide an expected duration and clarify
                   the range of uncertainty around the expected duration.

                                                                                                                          6
                   6.5.2.5 Group decision-Making techniques


                     Team-based approaches, such as brainstorming, the Delphi or nominal group techniques, are useful for engaging
                   team members to improve estimate accuracy and commitment to the emerging estimates. By involving a structured
                   group of people who are close to the technical execution of work in the estimation process, additional information
                   is gained and more accurate estimates obtained. Additionally, when people are involved in the estimation process,
                   their commitment towards meeting the resulting estimates increases.


                   6.5.2.6 reserve Analysis


                     Duration estimates may include contingency reserves, sometimes referred to as time reserves or buffers,
                   into the project schedule to account for schedule uncertainty. Contingency reserves are the estimated duration
                   within the schedule baseline, which is allocated for identified risks that are accepted and for which contingent or
                   mitigation responses are developed. Contingency reserves are associated with the “known-unknowns,” which may
                   be estimated to account for this unknown amount of rework. The contingency reserve may be a percentage of the
                   estimated activity duration, a fixed number of work periods, or may be developed by using quantitative analysis
                   methods such as Monte Carlo simulation (Section 11.4.2.2). Contingency reserves may be separated from the
                   individual activities and aggregated into buffers as shown in Figure 6-19.

                     As more precise information about the project becomes available, the contingency reserve may be used,
                   reduced, or eliminated. Contingency should be clearly identified in schedule documentation.

                     Estimates may also be produced for the amount of management reserve of time for the project. Management
                   reserves are  a specified amount of  the project  duration  withheld  for  management control purposes and are
                   reserved for unforeseen work that is within scope of the project. Management reserves are intended to address the
                   “unknown-unknowns” that can affect a project. Management reserve is not included in the schedule baseline, but
                   it is part of the overall project duration requirements. Depending on contract terms, use of management reserves
                   may require a change to the schedule baseline.












                   ©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK  Guide) – Fifth Edition   171
                                                                                       ®


                                           Licensed To: Jorge Diego Fuentes Sanchez PMI MemberID: 2399412
                                       This copy is a PMI Member benefit, not for distribution, sale, or reproduction.
   192   193   194   195   196   197   198   199   200   201   202