Page 196 -
P. 196

6 - PROJECT TIME MANAGEMENT






                         Analogous estimating is generally less costly and less time consuming than other techniques, but it is also
                      less accurate. Analogous duration estimates can be applied to a total project or to segments of a project and may
                      be used in conjunction with other estimating methods. Analogous estimating is most reliable when the previous
                      activities are similar in fact and not just in appearance, and the project team members preparing the estimates
                      have the needed expertise.



                      6.5.2.3 Parametric Estimating

                         Parametric estimating is an estimating technique in which an algorithm is used to calculate cost or duration
                      based on historical data and project parameters. Parametric estimating uses a statistical relationship between
                      historical data and other variables (e.g., square footage in construction) to calculate an estimate for activity
                      parameters, such as cost, budget, and duration.
                         Activity durations can be quantitatively determined by multiplying the quantity of work to be performed by labor
                      hours per unit of work. For example, activity duration on a design project is estimated by the number of drawings
                      multiplied by the number of labor hours per drawing, or on a cable installation, the meters of cable multiplied by the
                      number of labor hours per meter. For example, if the assigned resource is capable of installing 25 meters of cable
                      per hour, the duration required to install 1,000 meters is 40 hours. (1,000 meters divided by 25 meters per hour).

                         This technique can produce higher levels of accuracy depending upon the sophistication and underlying data
                      built into the model. Parametric time estimates can be applied to a total project or to segments of a project, in
                      conjunction with other estimating methods.


                      6.5.2.4 three-Point Estimating

                         The accuracy of single-point activity duration estimates may be improved by considering estimation uncertainty
                      and risk. This concept originated with the program evaluation and review technique (PERT). PERT uses three
                      estimates to define an approximate range for an activity’s duration:
                            •   Most likely (tM). This estimate is based on the duration of the activity, given the resources likely to be
                              assigned, their productivity, realistic expectations of availability for the activity, dependencies on other
                              participants, and interruptions.

                            •  optimistic (tO). The activity duration based on analysis of the best-case scenario for the activity.
                            •  Pessimistic (tP). The activity duration based on analysis of the worst-case scenario for the activity.


















             170      ©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK  Guide) – Fifth Edition
                                                                                          ®


                                           Licensed To: Jorge Diego Fuentes Sanchez PMI MemberID: 2399412
                                       This copy is a PMI Member benefit, not for distribution, sale, or reproduction.
   191   192   193   194   195   196   197   198   199   200   201