6 - PROJECT TIME MANAGEMENT







                                           Inputs         Tools & Techniques     Outputs
                                        .1  Schedule management      .1  Schedule network    .1  Schedule baseline
                                         plan              analysis         .2  Project schedule
                                        .2  Activity list  .2  Critical path method  .3  Schedule data
                                        .3  Activity attributes  .3  Critical chain method  .4  Project calendars
                                        .4  Project schedule       .4  Resource optimization    .5  Project management plan
                                         network diagrams    techniques      updates
                                        .5  Activity resource       .5  Modeling techniques  .6  Project documents
                                         requirements    .6  Leads and lags   updates
                                        .6  Resource calendars  .7  Schedule compression
                                        .7  Activity duration       .8  Scheduling tool
                                         estimates
                                        .8  Project scope statement
                                        .9  Risk register
                                        .10  Project staff assignments                                                    6
                                      .11  Resource breakdown
                                         structure
                                      .12  Enterprise environmental
                                         factors
                                      .13  Organizational process
                                         assets
                                   Figure 6-16 develop Schedule: Inputs, tools & techniques, and outputs





                                                         Project Time Management

                                                        6.1
                                                     Plan Schedule
                                                     Management
                                                    • Schedule            6.4
                                                      management plan
                                                                       Estimate Activity
                                                                        Resources
                                                        6.2
                                                       Define          • Activity resource
                                                      Activities         requirements
                                                                       • Resource breakdown
                                       11.2         • Activity list      structure
                                      Identify      • Activity attributes                Project
                                       Risks                                            Documents
                                      • Risk register   6.3               6.5
                                                      Sequence         Estimate Activity
                                                      Activities        Durations
                                       5.3
                                       Define
                                       Scope        • Project schedule  • Activity duration   7.2
                                                       network diagrams    estimates     Estimate
                                     • Project scope statement                            Costs
                                                                         • Project documents
                                                                           updates
                                       9.2                       6.6                      7.3
                                      Acquire                  Develop                   Determine
                                     Project Team              Schedule  • Project schedule  Budget
                                     • Project staff assignments
                                     • Resource calendars  • Organizational   • Project
                                                     process assets        management
                                                   • Enterprise   • Project    plan updates  12.1
                                       12.2         environmental     calendars  • Schedule baseline  Plan Procurement
                                                                  • Schedule
                                      Conduct        factors        data                Management
                                     Procurements                 • Project schedule
                                     • Resource calendars                                 4.2
                                                                 6.7                    Develop Project
                                                                Control                 Management
                                                                Schedule                  Plan
                                     Enterprise/
                                     Organization
                                            Figure 6-17. develop Schedule data Flow diagram


                   ©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK  Guide) – Fifth Edition   173
                                                                                       ®


                                           Licensed To: Jorge Diego Fuentes Sanchez PMI MemberID: 2399412
                                       This copy is a PMI Member benefit, not for distribution, sale, or reproduction.
   194   195   196   197   198   199   200   201   202   203   204