                   8.1.2.8 Meetings

                     Project teams may hold planning meetings to develop the quality management plan. Attendees at these
                   meetings  may  include the  project  manager; the  project  sponsor;  selected  project  team  members; selected
                   stakeholders; anyone with responsibility for Project Quality Management activities namely Plan Quality
                   Management, Perform Quality Assurance, or Control Quality; and others as needed.



                   8.1.3 Plan Quality Management: outputs


                   8.1.3.1 Quality Management Plan

                     The quality management plan is a component of the project management plan that describes how the     8
                   organization’s quality policies will be implemented. It describes how the project management team plans to meet
                   the quality requirements set for the project.

                     The quality management plan may be formal or informal, detailed, or broadly framed. The style and detail of the
                   quality management plan are determined by the requirements of the project. The quality management plan should
                   be reviewed early in the project to ensure that decisions are based on accurate information. The benefits of this
                   review can include a sharper focus on the project’s value proposition and reductions in costs and in the frequency
                   of schedule overruns that were caused by rework.


                   8.1.3.2 Process Improvement Plan

                     The process improvement plan is a subsidiary or component of the project management plan (Section 4.2.3.1).
                   The process improvement plan details the steps for analyzing project management and product development
                   processes to identify activities that enhance their value. Areas to consider include:

                        •   Process boundaries. Describe the purpose of the process, the start and end of the process, its inputs
                           and outputs, the process owner, and the stakeholders of the process.

                        •   Process configuration. Provides a graphic depiction of processes, with interfaces identified, used to
                           facilitate analysis.
                        •  Process metrics. Along with control limits, allows analysis of process efficiency.

                        •  targets for improved performance. Guide the process improvement activities.

















                   ©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK  Guide) – Fifth Edition   241
                                                                                       ®


                                           Licensed To: Jorge Diego Fuentes Sanchez PMI MemberID: 2399412
                                       This copy is a PMI Member benefit, not for distribution, sale, or reproduction.
   262   263   264   265   266   267   268   269   270   271   272