9 - PROJECT HUMAN RESOURCE MANAGEMENT
Preventive actions are those actions that are developed to reduce the probability and/or impact of problems
before they occur. These actions may include cross training to reduce problems during project team member
absences and additional role clarification to ensure all responsibilities are fulfilled.
9.4.3.2 Project Management Plan updates
Elements of the project management plan that may be updated include, but are not limited to, the human
resource management plan.
9.4.3.3 Project documents updates
Project documents that may indirectly be updated include, but are not limited to:
• Issue log, 9
• Roles description, and
• Project staff assignments.
9.4.3.4 Enterprise Environmental Factors updates
Enterprise environmental factors that may require updates as a result of the Manage Project Team process
include, but are not limited to:
• Input to organizational performance appraisals, and
• Personnel skill updates.
9.4.3.5 organizational Process Assets updates
Organizational process assets that may require updates as a result of the Manage Project Team process include,
but are not limited to:
• Historical information and lessons learned documentation,
• Templates, and
• Organizational standard processes.
©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK Guide) – Fifth Edition 285
®
Licensed To: Jorge Diego Fuentes Sanchez PMI MemberID: 2399412
This copy is a PMI Member benefit, not for distribution, sale, or reproduction.