Page 170 - Acquisition and Processing of Marine Seismic Data
P. 170

2.6 QC IN DATA ACQUISITION                         161

           a. Project information: Project and vessel name,  information on the cumulative details of
              study area, work day, contact name and       daily, weekly, monthly and overall project
              addresses, total survey area, total sail line  production times in terms of mobilization/
              of the survey in kilometers, estimated       demobilization (mob/demob), production,
              completion date of the survey, crossline     stand-by and downtimes (Table 2.19), brute
              coverage per sail line, basic acquisition
              parameters such as shot interval, minimum
              offset, number of streamers, streamer     TABLE 2.19  Statistical Information About the Overall
              separation, total array volume,           Project Progress in Hours and in Percentage Prepared for
              streamer length and depth, record length,  Daily Reports
              sampling rate, total number of recording
                                                                            Today       Cumulative
              channels, etc.
           b. Daily production details: A list of daily                 Hours  %       Hours  %
              completed or ongoing lines consisting of  Mobilization    00.00  00.00   186.00  28.50
              sequence number and line name(s), line    Demobilization  00.00  00.00   00.00  00.00
              direction, FSP (first shot point), LSP (last
                                                        Stand-by        00.00  00.00   140.40  21.50
              shot point), TSP (total shot point along the
              line), sail line length in kilometers, prime/  Downtime   02.45  11.46   16.20  2.50
              infill/reshoot areas in square kilometers and  Production-prime  04.30  18.76  216.10  33.10
              total full fold (FF), daily production in
                                                        Production-infill  10.25  43.39  26.45  4.20
              square kilometers (Table 2.18), remaining
              prime lines in kilometers overall project  Line change    06.20  26.39   66.25  10.20
              progress in percentage and completed and  Total           24.00  100.00  652.20  100.00
              remaining works (Fig. 2.104), statistical


           TABLE 2.18  Example List of Daily Production Details Prepared for Daily Activities Report

                                                                        2           2             2
           Seq.   Line            FSP   LSP   TSP    Length (km)  Infill (km )  Prime (km )  Total FF (km )
           042    DEG16-1442P1042  1511  3261  1751  43.775      0          21.8875     21.8875
           043    DEG16-1418P1043  1210  3423  2214  55.350      0          27.6750     27.6750
           044    DEG16-1388F1044  3220  3907  688   17.200      8.60       0           8.6000
           Total daily production             4653   116.325     8.60       49.5625     58.1625
           FSP is first shot point, LSP is last shot point, TSP is total shot point along the line, and FF is full fold.













           FIG. 2.104  Completed and remaining works prepared for daily reports. FF is full fold.
   165   166   167   168   169   170   171   172   173   174   175