Page 537 -
P. 537
QUEUING SIMULATION 517
Table 12.11 Simulation Results for Ten Customers for a Two-ATM System
Time
Available
Service
Interarrival Arrival Start Waiting Service Completion Time in ATM ATM
Customer Time Time Time Time Time System System 1 2
1 1.7 1.7 1.7 0.0 2.1 3.8 2.1 3.8 0.0
2 0.7 2.4 2.4 0.0 2.0 4.4 2.0 3.8 4.4
3 2.0 4.4 4.4 0.0 1.4 5.8 1.4 5.8 4.4
4 0.1 4.5 4.5 0.0 0.9 5.4 0.9 5.8 5.4
5 4.6 9.1 9.1 0.0 2.2 11.3 2.2 5.8 11.3
6 1.3 10.4 10.4 0.0 1.6 12.0 1.6 12.0 11.3
7 0.6 11.0 11.3 0.3 1.7 12.0 2.0 12.0 12.0
8 0.3 11.3 12.0 0.7 2.2 14.2 2.9 14.2 12.0
9 3.4 14.7 14.7 0.0 2.9 17.6 2.9 14.2 17.6
10 0.1 14.8 14.8 0.0 2.8 17.6 2.8 17.6 17.6
Totals 14.8 1.0 19.8 20.8
Averages 1.48 0.1 1.98 2.08
Table 12.11 shows that customer 7 is the first customer who has to wait to use an
ATM. We describe how customers 6, 7 and 8 are processed to show how the logic of
the simulation run for two ATMs differs from that with a single ATM.
Customer 6
l An interarrival time of 1.3 minutes is generated, and customer 6 arrives
9.1 þ 1.3 ¼ 10.4 minutes into the simulation.
l From the customer 5 row, we see that ATM 1 frees up at 5.8 minutes, and
ATM 2 will free up at 11.3 minutes into the simulation. Because ATM 1 is free,
customer 6 does not wait and begins service on ATM 1 at the arrival time of
10.4 minutes.
l A service time of 1.6 minutes is generated for customer 6. So customer 6 has a
completion time of 10.4 þ 1.6 ¼ 12.0 minutes.
l The time ATM 1 will next become available is set at 12.0 minutes; the time
available for ATM 2 remains 11.3 minutes.
Customer 7
l An interarrival time of 0.6 minute is generated, and customer 7 arrives
10.4 þ 0.6 ¼ 11.0 minutes into the simulation.
l From the previous row, we see that ATM 1 will not be available until 12.0
minutes, and ATM 2 will not be available until 11.3 minutes. So customer 7
must wait to use an ATM. Because ATM 2 will free up first, customer 7 begins
service on that machine at a start time of 11.3 minutes. With an arrival time of
11.0 and a service start time of 11.3, customer 7 experiences a waiting time of
11.3 11.0 ¼ 0.3 minute.
l A service time of 1.7 minutes is generated leading to a completion time of
11.3 þ 1.7 ¼ 12.0 minutes.
l The time available for ATM 2 is updated to 12.0 minutes, and the time
available for ATM 1 remains at 12.0 minutes.
Copyright 2014 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s). Editorial review has
deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.