76                                                       Chapter 2

                Correct for size.

                         (  63  V' 65
                       4
            CpBa = 1.4xl0  | ——— |  = $2,321
                         I  1,000 j
                Correct for inflation  from  January  1990 to mid-1998. Use  the  cost index for
            heat exchangers.

                      382.8
            CPU i = 2321 ———  =$2,387
                      372.2


                Correct for temperature (f T =  1.1), pressure (0), heat exchanger design (f D =
            0.8), and material of construction  (f~M = 1.0).

            C PAi = 1.1 (0 + 0.8) (1.0) (2387) = $2,101

                Calculate the installation factor.

            f n  = 2.0 (1.34) (1.18) = 3.162

            Condenser

            Repeat the above calculation for the condenser.
                         (  364  V- 65
            CpB2i=1.4xl0 4  I  ———  I  =  $7,258
                         I  IJOQOj
                      382.8
            C PBi = 7258  ——— =$7,465
                      372.2
            Cp Ai = 1.05 (0 + 0.8) (1.0) (7465) = $6,271


            f n  = (2.0) (1.34) (1.18) = 3.162