Page 93 - Chemical process engineering design and economics
P. 93

78                                                       Chapter 2


            Eductor-Mixer


            The  cost  of the mixer  is  given  as  $1000  FOB -  mid-1998.  No inflation  or  size
            correction is required.

            C PBi= $1,000

            C PAi = 1.1 (1.0)  (1.0)  (1.0) (1,000) = $1,100

            From  Table  2.8, the  direct-cost  factor  for  miscellaneous  equipment  for  carbon
            steel is 2.0.

              = 2.0(1.34)(1.18) = 3.162
            f u
            Installed  Cost

            Equation  2.15.5  gives  the  total  installed  cost  for  all  major  equipment  at  actual
            process conditions. As Figure 2.4.1 shows, there are two reactors and two air cool-
            ers.  Add all installed costs for the equipment at actual conditions.

            CM  = 2.056  (137,200)  +  2  (3.162)  (6,724)  +  3.162 (2101)  + 3.162 (6,271)  +  2
            (3.953) (9,613) + 4.427 (8,628) + 3.162 (1,100) = $468,800

                 Equation 2.15.6  gives the  total  installed  cost  for all major  equipment  at the
            base conditions. Add all installed costs for the equipment at the base conditions.

            CBI  =  2.056  (114,400)  +  2  (3.162)  (7,004)  +  3.162 (2,387)  +  3.162 (7,456)  +  2
            (3.953) (12,930) + 4.427 (7,844) + 3.162  (1,000) = $417,600

                 We see that the cost of the installation at ordinary process conditions, C Bi, is
            less than the cost at actual conditions, C AJ. If this process were a grass-roots plant,
            we  would  have  to  add  the  additional  cost  of buildings  and  auxiliary  facilities.  In
            this case, the process is a plant addition at an existing site where the buildings and
            auxiliary  facilities  are  available.  Therefore,  fAB  =  0,  as  given  in  Equation  8.15.8.
            Thus, the depreciable capital cost is equal to $468,800.

                 The fix capital cost equals the sum of the depreciable capital cost, land cost,
            and site development cost. Because this process will be built at an existing site, the
            land  cost  is  not  a  consideration.  Table  2.17 lists  site-development  factors  for  a
            plant at an existing site. For  a fluid processing plant, the factor  is 0.0211. Thus, the
            fixed  capital cost,


            C F = 468,800 + 0.0211 (468,800)  = $478,700




         Copyright © 2003 by Taylor & Francis Group LLC
   88   89   90   91   92   93   94   95   96   97   98