Page 613 - Corrosion Engineering Principles and Practice
P. 613

576    C h a p t e r   1 3                                                                                                        C a t h o d i c   P r o t e c t i o n    577


                         In principle, a Pearson survey can be performed with an impressed
                      CP  system  still  energized.  However,  sacrificial  anodes  should  be
                      disconnected since the signal from these may otherwise mask actual
                      coating defects. A three-person team is usually required to locate the
                      pipeline,  perform  the  survey  measurements,  place  defect  markers
                      into the ground and move the transmitters periodically.
                         By walking the entire length of a pipeline, an overall inspection of
                      the right-of-way can be  made together with the  measurements. In
                      principle,  all  significant  defects  and  metallic  conductors  causing  a
                      potential gradient will be detected. There are no trailing wires and
                      the impressed CP current does not have to be turned on and off.
                         The disadvantages associated with Pearson surveys are similar to
                      those of CIPS, as the entire pipeline has to be walked and contact
                      established with the ground. The technique is therefore unpractical in
                      many areas such as roads, paved areas, or rivers.

                      13.9.3   Direct and Alternating Current Voltage
                               Gradient Surveys
                      Direct current voltage gradient (DCVG) surveys are a more recent
                      method to locate defects on coated buried pipelines and assess their
                      severity. The technique again relies on the fundamental effect of a
                      potential  gradient  being  established  in  the  soil  at  coating  defects
                      under the application of CP current. In general, the greater is the size
                      of the defect, the greater is the potential gradient. The DCVG technique
                      is particularly suited to complex CP systems, for example, areas with
                      a relatively high density of buried structures. These are generally the
                      most difficult survey conditions. The DCVG equipment is relatively
                      simple and involves no trailing wires.
                         DCVG is measured by an operator between two reference elec-
                      trodes, typically copper sulfate electrodes, separated by a distance of
                      approximately 0.5 m. A pulsed DC signal is imposed on the pipeline
                      for DCVG measurements. The pulsed input signal minimizes inter-
                      ference from other current sources, such as CP systems, electrified
                      rail transit lines, telluric effects. This signal can be obtained with an
                      interrupter  on  an  existing  rectifier  or  through  a  secondary  current
                      pulse superimposed on the existing steady CP current.
                         The operator walking the pipeline observes voltage deflections
                      on a precision voltmeter to identify defect locations. The presence of
                      a  defect  is  indicated  by  an  increased  deflection  as  the  defect  is
                      approached, no deflection when the operator is immediately above
                      the defect and a decreasing deflection as the operator walks away
                      from  the  defect  (Fig.  13.40).  The  high  precision  in  locating  defects
                      (~0.1 to 0.2 m) represents a major advantage in minimizing the work
                      of subsequent digs if corrective action needs to be taken.
                         Alternating current voltage gradient surveys (ACVG) are similar to
                      the DCVG technique, except that in an ACVG survey, a low-frequency
                      transmitter is connected to the pipeline to create the AC signal.
   608   609   610   611   612   613   614   615   616   617   618