Page 270 - Decision Making Applications in Modern Power Systems
P. 270
Distributed generation in deregulated Chapter | 9 233
Method 1 Method 2 Method 3 Method 4 Method 5
100
Hosting capacity (kW) 60
80
40
20
0
Location 1 Location 2 Location 3
Measurement location
FIGURE 9.4 HC assessment using five different methodologies at three locations. HC, Hosting
capacity.
160
100% value 99th percentile 95th percentile
140
120
Hosting capacity (kW) 100
80
60
40
20
0
Location 1 Location 2 Location 3
Measurement location
FIGURE 9.5 The impact of using high percentiles of the examined PI on the HC achieved
levels. HC, Hosting capacity; PI, performance index.
Abad et al. [19] investigated the HC assessment considering various
uncertain parameters, namely, the uncertainty of the DG data resolution, the
DG size, and the DG integration. First, the data resolution effect was exam-
ined by considering two figures 30- and 60-minute data resolution. In the
30-minute approach the load profile and the DG output are recorded each for
half an hour. The authors concluded that increasing data resolution from