Page 384 - Decision Making Applications in Modern Power Systems
P. 384

346  Decision Making Applications in Modern Power Systems



              TABLE 13.3 (Continued)
              Planned maintenance pillar                  Evaluation/progress

              Evaluation/progress/criteria  Background/   Expected condition
                                       objective
              3. After completion, visually list  Facilitate service and  All motors, auxiliary
              and identify priorities A, B, or C  decision in the most  equipment, and
              to facilitate supervision  appropriate action to  facilities, classified in
                                       be taken, according to  A, B, and C with the
                                       priority           visual identification
                                                          labels, according to
                                                          the model approved
                                                          and adopted by the
                                                          company
              4. Identify the current state of  Rescue the ideal  Inspection/revision
              each engine, auxiliary   operating conditions of  planning in engines,
              equipment, and installation,  engines, auxiliary  equipment, and
              inspect/review and make  equipment, and     facilities A to redeem
              necessary repairs to maintain in  facilities, improving  desired conditions
              perfect operational conditions  availability, reliability,  Action plan defined
                                       and maintenance
                                                          with: activities,
                                                          materials, deadlines,
                                                          time provided in each
                                                          repair activity and
                                                          maintenance team
              5. Elaborate the most indicated  Define a maintenance  Equipment A, B, and
              maintenance procedures for  philosophy to be used  C classified and with
              each engine, auxiliary   in equipment A, B, and  the type and
              equipment, and facilities, as  C according to priority  recommended
              recommended in the master                   maintenance plan
              plan                                        completed
              Consider those in the technical
              manuals, MaMa2i and create
              those that do not exist and are
              necessary
              6. Start the required activities  Organize maintenance  Planning and schedule
              for each engine, auxiliary  and update the data of  of activities for
              equipment, and installation A.  each engine, auxiliary  engines, auxiliary
              Follow the MaMa2i plan and  equipment, and  equipment, and
              add nonexisting services to the  installation A, creating  facilities A completed
              system                   history, technical  and started
                                       inspection standards
                                       and maintenance
                                       procedures
                                       Follow template
                                       created by engineers
                                       for reference
   379   380   381   382   383   384   385   386   387   388   389