Page 266 - Defrosting for Air Source Heat Pump
P. 266

260                                         Defrosting for Air Source Heat Pump

         as the experimental procedures. Then, five designed continuous cases were listed.
         After these observed, measured and calculated results were presented, the system
         energy and stability performances as well as the defrosting starting indexes were com-
         paratively discussed and analyzed. The conclusions of this work were finally given.



         9.2.1 Experimental cases
         To investigate the frost accumulation influence on RCD performance, experimental
         works were carried out using the described experimental ASHP unit. First, it was nec-
         essary to ensure that the frost accumulations on the surface of the outdoor coil were
         different to reach meaningful experimental results. It could be reached by two
         methods. One is changing the relative humidity of the outdoor air in the experiment
         because water vapor in the outdoor air is the source of frost. But the relative humidity
         was always kept at a fixed value during frosting for comparison. Finally, another
         method is changing the duration of the frosting mode, which was taken in this work.
         In a real application, a time-based RCD is always started after frosting for 60–90 min.
         However, the relative humidity of the ambient air is always at 40%–80%, which is
         much lower than 90%. Therefore, in this study, the frosting durations were designed
         to be a little shorter, at 50–70 min.
            Second, for each circuit, frost accumulations over their surfaces should be similar
         at different experimental cases. The FEC should be nearly the same in the different
         experimental cases. For an ASHP unit with a multicircuit outdoor coil, the FEC is hard
         to adjust due to many parameters affecting frosting performance, including the struc-
         ture of the heat exchanger, the type of fin and its surface, the distribution of air and
         refrigerant, etc. However, the refrigerant flow to each circuit could be varied by
         adjusting the opening degree of the modulating valves, and thus adjusting the frost
         accumulations and FEC. Therefore, in this study, a set of fixed valve opening degrees
         was finally obtained by trial-and-error manual adjustments of the opening degrees of
         the valves. With this operational method, the FEC was successfully controlled at
         higher than 90%. For each circuit, the frost accumulation difference was less than
         5%. After the opening degree was fixed, the water-collecting Cylinder D was placed
         under Circuit 3 during defrosting. Then, a meaningful and effective experimental case
         was conducted. Finally, the entire procedure of an experimental case is clearly illus-
         trated in Fig. 9.2.
            As shown in Fig. 9.2, the experimental ASHP unit was first operated at frosting
         mode, at an air dry-bulb temperature of 0.5   0.2°C and a relative humidity of
         90   3%. This ambient condition was jointly maintained by the use of experimental
         ASHP unit, the LGUs, and humidifiers placed in the outdoor frosting space. Mean-
         while, the indoor air temperature was maintained at 20   0.2°C by jointly using
         the ASHP unit and the existing DX A/C system. Before frosting was terminated,
         the opening degrees of valves could be adjusted as required. Before initiating the
         defrosting operation, the FEC should be controlled at a value of higher than 90%.
         In order to keep the system stable and safe, the four-way valve was switched to
         defrosting mode after compressor shutdown for 1 min. It cost about 4 s before the
         compressor was powered on again, and then a defrosting operation started. In this
   261   262   263   264   265   266   267   268   269   270   271