Page 293 - Failure Analysis Case Studies II
P. 293

278























                       Fig. 1.  Photograph of the pipe-to-flange joint (arrow shows the leaking portion).

          2.1. Observations
            The leaking joint, removed from the assembly line, was found to have a crack in the pipe portion
          adjacent to the pipe-to-flange weld. Figure 2 shows a stereomicroscopic view of the crack. Table 1
          shows the chemical analysis of the material of the components.
            The chemical analysis of the  material  from  the flange portion  conforms  to AISI  304L grade,
          whereas that from the pipe portion  conforms to AISI  304 grade only. The whole component is
          exposed to 90% HNOS at room temperature.  The component had a crack 5mm long in the pipe
          portion, about 4mm away from the weld between the flange and the pipe. The component was cut
          open to reveal the inside portion of the pipe. It was noticed that the inside surface of the pipe had
          a corroded band about 7 mm in width throughout the inner circumference of the pipe, and the crack





                         l











                                                                      I




                           Fig  2  Stereomicrograph of the crack on a pipe-to-flange joint  x 16

                           Table 1  Chemical analysis (wtX) of the failed pipe-to-flange joint
             Component    C        S       Cr       Ni      Mn      Mo       Fe
             ~~   ~~~
             Flange      0 034   0 010    19 3     98       13       03     Balance
             Pipe        0 093   0011      19 7    94       12       02     Balance
   288   289   290   291   292   293   294   295   296   297   298