Page 457 - Subyek Teknik Mesin - Forsthoffers Best Practice Handbook for Rotating Machinery by William E Forsthoffer
P. 457

Be st Practice 7 .27
       Be st Practice 7 .28          Lube, Seal and Control Oil System Best Practices


         Best Practice 7.27Practice 7.27
         Best
         Perform an oil system site audit if the subject system has  Lessons Learned
         caused critical machinery unit shutdowns in the past that  Continuing critical machinery unit oil system reliability
         have resulted in lost product revenue.             issues need to be evaluated in terms of lost revenue costs
           Use the original equipment manufacturer (OEM) or a qualified  to justify an oil system site audit to discover root causes
         consultant to review past problems and conduct a site audit to cover  and corrective action.
         the following items as a minimum:
           Determine the present operating condition of each system  Benchmarks
           component
                                                            I have performed site auxiliary system audits since 1990 for the reso-
           Verify that all set points are as specified in the instruction manual
                                                            lution of long term reliability issues that have lost the end user large
           Check component selection, where required and verify proper
                                                            amounts of revenue. This procedure has resulted in oil system and
           component sizing
                                                            machinery unit reliabilities of 99.7%þ.
           Define a remedial action plan which in addition may include:
           Off-line testing at the first opportunity
           Requests for additional component sizing information from the
           OEM
           Modifications to the operating procedure for this oil system


       B.P. 7.27. Supporting Material

       See B.P: 7.5 for oil system component audit information
       guidelines.











         Best
         Best Practice 7.28Practice 7.28
         Be sure to require all oil system interconnecting supply and  Lessons Learned
         drain piping to have maximum oil velocities set to prevent  Lower than anticipated unit reliability and safety issues
         excessive pressure drops, which will affect control valve  (plant fires) have resulted from improper sizing of inter-
         sizing and expose bearing brackets to flooding (possible  connecting oil piping.
         split line oil leaks).                               The use of smaller than required interconnecting oil supply pipes
           The maximum velocity values are:                 has resulted in backpressure (bypass) valve replacement due to the
           Supply piping e Maximum 6 ft/second              higher pressure necessary to force the oil up to the unit and corre-
           Drain piping e Maximum 1 f/second                sponding low valve opening causing valve noise and/or wear and or
           Our best practice recommendation is therefore to include inter-  instability.
         connecting oil piping design and manufacture in the machinery vendor  Additionally, fires have been experienced in steam turbine appli-
         scope of supply.                                   cations on the steam inlet end, when bearing bracket oil leaks were
           Oil system vendor backpressure and supply valve sizing is based  caused by drain oil piping being smaller than required, which raised the
         on assumed interconnecting oil pressure drops.     oil levels in the bearing bracket to the split line.
           If the interconnecting piping is not sized properly and has greater
         pressure drop than anticipated during the selection of the control  Benchmarks
         valves, the control valves may not be properly sized.  This best practice has been used since the mid-1980s when I was
           Improper control valve sizing will affect valve transient response  involved with the start-up of a large petrochemical plant. Allowing the
         and stability leading to lower than anticipated unit reliability.  contractor (EP&C) to select and manufacture the interconnecting
           In addition, higher than anticipated interconnecting drain pipe  supply oil piping resulted in having to throttle the backpressure control
         pressure drop can raise the level of oil in the bearing bracket and cause  valve inlet block valve to prevent valve noise, wear and instability, until
         split line oil leaks that can expose the machinery and environment to  the valve could be resized for a smaller trim at the first turnaround
         fires in hot service areas (steam turbine surfaces and pipes).  (three years of exposure to unnecessary unit trips caused by improper
                                                            valve response during transient conditions). Since that time, this best
                                                            practice has been used on all new projects to ensure maximum unit
                                                            reliability (99.7% or greater).



           428
   452   453   454   455   456   457   458   459   460   461   462