Page 77 - Fundamentals of Magnetic Thermonuclear Reactor Design
P. 77

60     Fundamentals of Magnetic Thermonuclear Reactor Design























            FIGURE 3.19  VV sector and TFCs assembly. (Copyright ITER Organization, 2017).


            3.8  REACTOR ASSEMBLY
            More than 160 pieces of machinery are involved in the ITER assembly, testing and
            moving works, including tilters, crossbeams, fixing means and adjusting devices.
               The lifting system includes two bridge cranes mounted on rails that run the
            entire length of the tokamak buildings, pre-assembly and intermediate testing
            sites to form a 175-m-long crane bay. Every crane has two  independent cargo
            trucks with a carrying capacity of 375 t each. Together, the cranes can handle
            loads of up to 1500 t. The heaviest single loads are the ‘sub-assembly’ tool
            module and the cryostat base section, which weigh 1250 and 1200 t, respec-
            tively. In some cases, components standing 20 m high and weighing hundreds
            of tons have to be manoeuvred into required positions within tolerances of
            3 mm. The CS will be the tallest lift of assembly operations (18.2 m).
               Special sub-assembly tools are employed to pre-assemble the vacuum vessel
            sectors together with the TF coils (Fig. 3.19).
               One such tool will suspend a VV sector from its top, install associated
            thermal shielding and rotate TF coils into position on the left and right sides
            of the sector using supports moving on a pivoting rail. Upon installation and
              anchoring of the TF coils, the 22-m-tall sub-assembly tool will be placed on a
            pedestal (Figs 3.20 and 3.21) by the bridge cranes.
               This procedure is repeated until all the VV sectors are mounted. A tilter and
            two sub-assembly tools are projected to carry out the above operations in 90 days.


            APPENDIX A.3.1 QUALITY ASSURANCE PROGRAMME
            FOR REACTOR DESIGN

            Complex processes, high technological level and therefore stringent technical
            and safety requirements have characterised fusion power engineering from the
            onset. The many years of experience internationally indicates that it is not only
   72   73   74   75   76   77   78   79   80   81   82