Page 29 - Handbook of Electrical Engineering
P. 29

8    HANDBOOK OF ELECTRICAL ENGINEERING

                             Table 1.8.  Master load schedule for the high voltage main switchboard

              Description of load            No. of  Nameplate   Continuous   Intermittent  Standby
                                             units    ratings of   power        power       power
                                                      each unit   consumed    consumed    consumed
                                                       (kW)         (kW)        (kW)        (kW)
              HV motor loads
              Main oil expert pumps            3        650         1300           0         650
              Gas compressor                   4        500         1500           0         500
              Seawater lift pumps              4        450         1350           0         450
              LV motor loads
              Feeder to drilling               1          0         2700        2400        1000
              Feeder to LV process MCC         2          0         1652         319        1077
              Feeder to LV utilities MCC       1          0         1013         320         633
              Feeder to LV emergency MCC       1          0          168         179          58

              Sub-totals                                            9983        3218        4368
              Totals for the main generator to supply = (1.0 × 9983) + (0.5 × 3218) + (0.1 × 4368) = 12,029 kW

                    During the detail design phase of the project the load schedules will be modified and additional
              loads will inevitably be added. At least 10% extra load should be added to the first estimate i.e.
              1203 kW. The total when rounded-up to the nearest 100 kW would be 13,300 kW.

                    Sufficient generators should be installed such that those that are necessary to run should be
              loaded to about 80 to 85% of their continuous ratings, at the declared ambient temperature. This
              subject is discussed in more detail in sub-section 1.3. If four generators are installed on the basis that
              one is a non-running standby unit, then three must share the load. Hence a reasonable power rating
              for each generator is between 5216 kW and 5542 kW.


              1.3 DETERMINATION OF POWER SUPPLY CAPACITY

              After the load has been carefully estimated it is necessary to select the ratings and numbers of
              generators, or main incoming feeders from a power utility company. Occasionally a plant may require
              a combination of generators and incoming feeders e.g. refinery, which may operate in isolation or in
              synchronism with the utility company.
                    Usually a plant has scope for expansion in the future. This scope may be easy to determine
              or it may have a high degree of uncertainty. The owner may have strong reasons to economise
              initially and therefore be only willing to install enough capacity to meet the plant requirements in
              the first few years of operation. If this is the case then it is prudent to ensure that the switchgear in
              particular has adequate busbar normal current rating and fault current rating for all future expansion.
              The main circuit breakers should be rated in a similar manner. If the switchgear is rated properly at
              the beginning of a project, then all future additions should be relatively easy to achieve in a practical
              and economical manner. Such an approach also leads to a power system that is easy to start up,
              operate and shut down.
                    The supply capacity normally consists of two parts. One part to match the known or initial
              consumption and a second part to account for keeping a spare generator or feeder ready for service.
   24   25   26   27   28   29   30   31   32   33   34