Page 30 - Handbook of Electrical Engineering
P. 30

ESTIMATION OF PLANT ELECTRICAL LOAD     9

           Any allowance required for future load growth should be included in the power consumption calcula-
           tions. This two-part approach is often referred to as the ‘N − 1 philosophy’, where N is the number
           of installed generators or feeders. The philosophy is that under normal operating conditions in a fully
           load plant N − 1 generators or feeders should be sufficient to supply the load at a reasonably high
           load factor.

           Let P l = power consumption required at the site ambient conditions
                P g = rated power of each generator or feeder at the site ambient conditions
                F o = overload power in % when one generator or feeder is suddenly switched out of service
                F i = load factor in % of each generator or feeder before one is switched out of service
                N = number of installed generators or feeders. N is usually between 4 and 6 for an
                     economical design of a generating plant and 2 or 3 for feeders.
                 P l and P g are usually the known variables, with F i and F o being the unknown variables.
           Several feasible ratings of P g may be available and the value of N may be open to choice. A good
           choice of P g and N will ensure that the normally running load factor is high i.e. between 70% and
           85%, whilst the post-disturbance overload on the remaining generators or feeders will not be so high
           that they trip soon after the disturbance, i.e. less than 125%.
           The initial load factor can be found as,

                                                    100P l
                                             F i =         %
                                                  P g (N − 1)
           The post-disturbance overload can be found as,

                                                    100P l
                                             F o =         %
                                                  P g (N − 2)
                 If it is required that F i is chosen for the design such that F = 100% and no overload occurs
           then let F be called F i100 and so,
                                          (N − 2)100
                                   F i100 =            for no overloading.
                                             N − 1
                 Table 1.9 shows the values of F i against N for the no overloading requirement.

                                    Table 1.9.  Selecting N and F i100 on the
                                    basis of N − 1 capacity with overloading not
                                    tolerated
                                    No. of installed   Value of F i100 to
                                    generator or     ensure no overloading
                                    feeders N              F i100 %
                                          2             Not practical
                                          3                50.0
                                          4                66.67
                                          5                75.00
                                          6                80.00
                                          7                83.33
                                          8                86.71
   25   26   27   28   29   30   31   32   33   34   35