Page 26 - Handbook of Electrical Engineering
P. 26

ESTIMATION OF PLANT ELECTRICAL LOAD     5

                                   Table 1.4.  Diversity factors for load estimation

                     Type of project             D c for C sum  D i for I sum  D s for S sum
                     Conceptual design of a new  1.0to1.1      0.5to0.6      0.0to0.1
                       plant
                     Front-end design of a new   1.0to1.1      0.5to0.6      0.0to0.1
                       plant (FEED)
                     Detail design in the first half of  1.0to1.1  0.5to0.6   0.0to0.1
                       the design period
                     Detail design in the second half  0.9to1.0  0.3to0.5    0.0to0.2
                       of the design period
                     Extensions to existing plants  0.9 to 1.0  0.3 to 0.5   0.0 to 0.2


                 The above method can be used very effectively for estimating power requirements at the
           beginning of a new project, when the details of equipment are not known until the manufacturers can
           offer adequate quotations. Later in a project the details of efficiency, power factor, absorbed power,
           rated current etc. become well known from the purchase order documentation. A more accurate form
           of load schedule can then be justified. However, the total power to be supplied will be very similar
           when both methods are compared.
                 The total load can be considered in two forms, the total plant running load (TPRL) and the
           total plant peak load (TPPL), hence,

                                         n

                                TPRL =     (D c C sumj + D i I sumj ) kW
                                        j=1
                                         n

                                TPPL =     (D c C sumj + D i I sumj + D s S sumj )  kW
                                        j=1
           Where n is the number of switchboards.

                 The installed generators or the main feeders to the plant must be sufficient to supply the TPPL
           on a continuous basis with a high load factor. This may be required when the production at the plant
           is near or at its maximum level, as is often the case with a seasonal demand.

                 Where a plant load is predominantly induction motors it is reasonable to assume the overall
           power factor of a switchboard to be 0.87 lagging for low voltage and 0.89 lagging for high voltage
           situations. If the overall power factor is important with regard to payment for imported power, and
           where a penalty may be imposed on a low power factor, then a detailed calculation of active and
           reactive powers should be made separately, and the total kVA determined from these two totals. Any
           necessary power factor improvement can then be calculated from this information.


           1.2.1 Worked Example


           An offshore production and drilling platform is proposed as a future project, but before the detail
           design commences it is considered necessary to prepare an estimate of the power consumption. The
           results of the estimate will be used to determine how many gas-turbine driven generators to install.
   21   22   23   24   25   26   27   28   29   30   31