ESTIMATION OF PLANT ELECTRICAL LOAD     7

           This in turn will enable an initial layout of all the facilities and equipment to be proposed. Since this is
           a new plant and the preliminary data is estimated from process calculations, mechanical calculations
           and comparisons with similar plants, it is acceptable to use the following diversity factors, D c = 1.0,
           D i = 0.5and D s = 0.1.
                 Tables 1.5, 1.6, 1.7 and 1.8 show the individual loads that are known at the beginning of
           the project.
                 The total power is found to be 12,029 kW. At this stage it is not known whether the plant is
           capable of future expansion. The oil and gas geological reservoir may not have a long life expectation,
           and the number of wells that can be accommodated on the platform may be limited. The 4000 kW
           of power consumed by the drilling operations may only be required for a short period of time e.g.
           one year, and thereafter the demand may be much lower.

                      Table 1.7.  Subsidiary load schedule for the low voltage emergency switchboard
           Description of load            No. of   Nameplate   Continuous  Intermittent  Standby
                                           units   ratings of    power       power       power
                                                    each unit  consumed     consumed   consumed
                                                     (kW)        (kW)        (kW)        (kW)
           Emergency lighting               1          75          75           0          0
           Chlorine generator               1 ∗        30          30           0          0
           Desalination unit                1 ∗        75          75           0          0
           Potable water pumps              1          5           5            0          0
           Instrument air compressors       1          90          90           0          0
           Instrument air driers            1          10          10           0          0
           Living quarters feeder-B(off)    1 ∗       500          0            0          0
           Living quarters emergency feeder  1        100          50          50          0
           Living quarters hot water pumps  1          15          15           0          0
           Diesel fuel transfer pump        1          5           5            0          0
           Emergency diesel eng. sump heater  1        3           3            0          0
           Emergency diesel gen. auxiliaries  1        2           0            0          2
           Emergency diesel eng. bat. charger  1       1           0            1          0
           Emergency diesel eng. room fans  2          11          11           0          0
           Control room fans                2          22          22           0          0
           Computer UPS supply              1          5           5            0          0
           Emergency radio supplies         1          10          0            0         10
           Navigation aids UPS supply       1          10          10           0          0
           Life boat davit supplies         2          37          0           50         24
           Life boat diesel heater supplies  2         4           4            4          0
           Fire pump engine battery chargers  2        22          22          22          0
           Seawater washdown pump           1 ∗        37          0           37          0
           Anti-condensation swbd heaters   —          25          25           0          0
           Anti-condensation motor heaters  —          25          10          15          0
           Portable lighting supplies       1          1           1            0          0

           Sub-totals for the switchboard                         468         179         58
           Normal running load for the switchboard = (1.0 × 468) + (0.5 × 179) + (0.1 × 58) = 563 kW
           For black start delete loads marked ( )
                                       ∗
           Black start sub-totals for the switchboard = (1.0 × 363) + (0.5 × 142) + (0.1 × 0) = 434 kW