252    CHAPTER 10 A reliable analysis method





                         4 RESULTS AND DISCUSSION
                         A heavy shovel is employed to simulate and validate the model against static and test
                         data. The fatigue lives of front-end hot spots are then estimated. The structural
                         dynamics of the shovel is simulated using the hoist rope force and swing motion
                         as inputs. The dynamic stresses of front-end structural hot spots are recovered and
                         compared with the static and test results reported by Zhang [21], where (i) the static
                         stresses of boom and handle were calculated for the shovel; and (ii) the dynamic
                         stresses of boom and handle were investigated by analyzing field test data on the
                         shovel. The details are presented below.

                         4.1 SIMULATION AND VALIDATION OF FRONT-END MODEL
                         Figure 10.10a and b indicates the dynamic loading on the front-end model in the local
                         coordinate system o (x,y,z) during the one working cycle of 60 s. They consist of
                         Figure 10.10a with the load at the hoist rope; and Figure 10.10b, the swing angular
                         displacement at the revolving center o in the y direction.
                                       450
                                       400
                                      Hoist rope tension (KN)  300
                                       350

                                       250
                                       200
                                       150
                                       100
                                        50
                                         0
                                          0     10    20      30    40     50   60
                                    (a)                    Time (s)
                                        90
                                        80
                                        70
                                        60
                                      Angle (°)  50
                                        40
                                        30
                                        20
                                        10
                                         0
                                          0     10    20     30    40    50     60
                                    (b)                   Time (s)
                         FIGURE 10.10
                         Dynamic loads on the shovel front-end with time: (a) load at hoist rope and (b) swing angular
                         displacement at the revolving center.