Page 813 - Industrial Power Engineering and Applications Handbook
P. 813

23/768 Industrial Power Engineering and Applications  Handbook
         impracticable to keep a close monitoring of such system   again. This switching is therefore more stressful for the
         variations and alter the capacitive reactance manually to   capacitor as well as for the system, due to surge voltages.
         maintain the desired p.f. level.               During a switch ON therefore some time delay must be
           The situation in an HT installation will, however, be   introduced  into the switching  circuit  for the  capacitor
         different. An HT system is mostly a fixed-load one, where   charge  to  decay  to  a  safe  level.  In  this  sequence, the
         a  variation  in  the  load  may  be only  occasional  and  at   capacitors of  each  step are normally  the  same. It  is  a
         certain  periodic  intervals.  To  provide  an  automatic   primitive  and  unscientific  switching  sequence  and
         switching in such cases will be a costly arrangement due   therefore not in much use.
         to expensive switchgear equipment. In addition, it will
         also  cause  cumulative  switching surges  as  a  result  of   23.16.2  True ‘first in first out’ (FIFO)
         rapid reclosing and interrupting sequences unless a static
         switching control is adopted as discussed in Section 24.10,   Capacitors  are  switched ON in  the  sequence of  1-2-3
         which  will  further  add  to  the  cost.  To  mitigate  such   . . . . n but an additional logic is used to switch OFF in
         constraints, the following may be considered as the more   the same sequence 1-2-3 . . . n, i.e. the oldest OFF capacitor
         recommended methods for p.f. control of such installations:   is  switched  ON  first  and  the  oldest  ON  capacitor  is
                                                        switched OFF first. This apparently is the best switching
          1  Identify the likely variations in load and p.f. during a   sequence, giving enough  time  to  an OFF capacitor  to
            24-hour  period.  Maintain  a  minimum  fixed  kVAr   discharge before it is switched again. Each stage capacitor
            permanently connected in the system, at the distribution   rating must be equal to avoid a wide fluctuation in the
            point for the likely constant loads. For the rest, the   p.f.  correction  and  hence  undesirable  subsequent
            banks  may  be  selected  so that only  one or two are   switchings, which may be necessitated when the capacitors
            sufficient to control the whole system for the desired   are not of equal ratings.
            p.f.  level  or system regulation.  This will  also limit
            operations  of  the banks to only  three or four a day   23.16.3  Pseudo (false) ‘first in first out’
            and less than a thousand during a year, as recommended
            in Section 26.1(2). Control may now be carried out:   In  a way this is more appropriate than the FIFO, for it
              Manually, as  variations  in  load  would  almost  be   can have unequal stage capacitors. Capacitors, however,
                                                        are arranged in ascending order such as  10, 20, 50 . . .
              specific and periodic and easy to monitor or
              By  making  it  automatic,  which  would  now  be   kVAr etc., or large or small capacitors. But, as mentioned
              economical with one or two variable banks.   above, this may  not provide  accurate correction in the
         2  In a secondary transmission or a primary distribution   first instance. Now the relay may have to operate on the
            network it is common practice to provide the maximum   theory of probability and resort to a lot of sequencing to
            possible  size of  fixed  capacitor banks  at  the  trans-   arrive at the  right  correction.  Such a sequencing may
            mission point or on the pole at the distribution point   also lead to hunting and cause voltage fluctuations, because
            with the feeder transformer. This is done to maintain   of  varying p.f.  s and also cause switching currents and
            the p.f. and the regulation of the system up to a certain   voltage surges.
            minimum level. Capacitors mounted out of  sight or
            away from easy reach may sometimes be ignored for   23.16.4  1+2+2. . .
            maintenance or periodic checks. This must be taken
            into account while installing the capacitor units. To   The first capacitor is half  the  rating  of  the  remaining
            monitor the health of capacitor units one may install   ones, which are all equal. The p.f. correction is delayed,
            an ammeter or a kVAr meter in each phase and maintain   due to allowing discharge time. The smallest unit is more
            a  logbook to  monitor  the health  of  capacitor  units/   stressed.
            banks through the  unbalance  in  the three  phases  of
            the  capacitor  circuit.  When  warranted,  preventive   23.16.5  Direct  combinatorial  or  auctioneering
            measures such as cleaning the insulators, tightening   switching
            the terminals, and replacing or adding of a few capacitor
            units to make up for the lost capacitances and to balance   Here the relay assesses the kVAr requirement of the system
            the system can be undertaken.               and  switches  ON  all  the  required  capacitors
                                                        simultaneously. Theoretically any size of capacitor units
                                                        can  be  used.  But  when  a  capacitor  is  taken  out  for
         23.1 6  Switching sequences                    maintenance,  this  can  create  confusion  in  the  p.f.
                                                        correction. The relay  will  not be aware of  this and act
         A switching sequence that can be employed for a particular   accordingly. The bank size may also be large and cause
         load cycle may be one of the following:        switching surges.
         23.16.1  First  in  last  out                  23.16.6  Special sequencing
         This is  the  simplest  type  of  switching.  Capacitors  are   These are sequencers and can sequence the switching of
         switched ON in the sequence of  1-2-3 . . . n and switched   capacitors  in  any  fixed  pattern.  Capacitors  can  be
         OFF in  the  reverse  sequence i.e.  n  . . . 3-2-1.  In  this   automatically taken out of the circuit and others introduced
         switching the last switched capacitor is made to switch   in their place by  a device known as ‘the load rotator’.
   808   809   810   811   812   813   814   815   816   817   818