Page 231 - Materials Chemistry, Second Edition
P. 231

L1644_C05.fm  Page 204  Monday, October 20, 2003  12:02 PM











                                     TABLE 5.14
                                     Statistical Parameter Describing Results of the Environmental Damage
                                     Estimation in Scenarios 1 and 2 as External Costs a

                                               Parameter               Scenario 1 b       Scenario 2 c
                                     Normal mean                         3.73               0.87
                                     Normal standard deviation           5.16               1.08
                                     Geometric mean                      2.19               0.55
                                     Geometric standard deviation        2.81               2.62
                                     Minimum                             0.087              0.029
                                     Maximum                           221.7               74.4
                                     Median                              2.09               0.53

                                                             68% Confidence interval
                                     Superior                            6.15               1.44
                                     Inferior                            0.78               0.21
                                     a mU.S.$ per kWh (1E-3 U.S.$/kWh).
                                     b Without filters.
                                     c With filters.

                                    been made in one separate run per scenario. Because of the inherent variability of the
                                    Monte Carlo model, it is not possible to affirm that the set of values for the input
                                    variables used in the run of Scenario 2 (current situation) will be the same as those
                                    used in Scenario 1 (former situation). The same was done with the calculation of LCI
                                    uncertainties and, due to the generation of random numbers, every run occurs in a
                                    different way. In order to verify the importance of this variability on the final outcome,
                                    both simulations have also been made in one run; it could be checked that the results
                                    are the same because the variations are negligible.
                                       Figure 5.16 presents the first result, which is the case of the incineration process
                                    supported by the advanced AGTS. In the x-axis, it is possible to observe the envi-
                                    ronmental damage cost per energy output. The y-axis shows the probability of each
                                    cost value. The mean of the environmental damage cost in Scenario 2 is 0.87 mU.S.$
                                    per kWh (with m = 10 ). The total number of iterations carried out with the software
                                                     –3
                                    Crystal Ball is 10,000. A summary of all the results generated can be found in Table
                                    5.14. The geometric standard deviation from them is 2.62.
                                       The second case occurs in time before the first one, when the incinerator did
                                    not have an advanced AGTS. The emissions of pollutants were more important and
                                    consequently the environmental damage cost is much higher, with 3.73 mU.S.$ per
                                    kWh. The probability distribution of this result can be found in Figure 5.17. This is
                                    explained because the only important change corresponds to the mean values of 10
                                    parameters, including pollutants and electricity production, which are lower with an
                                    advanced AGTS installed.


                                    © 2004 CRC Press LLC
   226   227   228   229   230   231   232   233   234   235   236