Page 394 - Offshore Electrical Engineering Manual
P. 394

CHAPTER


                  Protection, Monitoring                                     6

                  and Control






                  PRECOMMISSIONING
                  Before commissioning, it is essential that the installation work has been properly
                  checked before any equipment or cables are energised. Cable connections are ‘rang
                  through’ and cable insulation is checked where possible. Hard-wired logic and con-
                  trol and monitoring software must be checked, although this may be limited to criti-
                  cal circuits if the factory acceptance tests are comprehensive and well documented.
                  The ‘sense’ of any current transformers must be checked to ensure terminals are not
                  reversed.
                    All such work is termed precommissioning.



                  PERMIT-TO-WORK SYSTEMS
                  Monitoring of all work being done (and being aware of all possible clashes) during
                  the major shutdown of an installation is vital to the safety of all personnel, and a
                  failure in the control of work was a major contributor to the Piper Alpha disaster. The
                  three-dimensional aspect of working offshore can make the control of work even
                  more difficult, and the permit controller is second only to the offshore installation
                  manager in having the most responsible job during a shutdown.
                     Let us consider two examples:

                   •   Radiography with radioactive sources – what is the extent of the area that
                     must be barriered off, and how many platform decks are affected at any one
                     time?
                   •   What isolations are required to replace a valve on a fuel-gas system – how many
                     other systems are affected? Will main generation be affected? How many disci-
                     plines are involved?

                     These are only a few of the questions which require consideration if such
                  tasks are to be completed safely. Even forgetting one could lead to injury or
                  death.
                     For more information refer to the Health and Safety Executive’s ‘The safe isola-
                  tion of plant and equipment’.





                  Offshore Electrical Engineering Manual. https://doi.org/10.1016/B978-0-12-385499-5.00045-5  381
                  Copyright © 2018 Elsevier Inc. All rights reserved.
   389   390   391   392   393   394   395   396   397   398   399