444    CHAPTER 2  Preparation and Use of Performance Standards





                                  Parameter         Example of Equipment/Systems Appropriate to Parameter
                          Equipment Performance   Generators
                          Standard of Equipment   TEMPSC communications, Standby Vessel communications
                          Suitability of equipment for   Electrical equipment in potentially  hazardous areas, Ingress protection
                          operating environment   of equipment
                          Adequately/correctly Sized   Switchboards, cables, motors, UPS batteries
                          Initiate other actions   Executive actions initiated by fire/gas detection system or by detection
                                                 of process deviation
                          Closure Time           Valves, fire dampers (by actuators)
                          Failure Mode           Valve position on loss of power or pressure in actuating medium
                          Response Time          Detectors, equipment trip, blowdown
                          Duration               For emergency lighting, survivability of RESDVs and TR
                          Location/orientation   Emergency  control  points,  HVAC  inlets  relative  to  hazardous  areas,
                                                 emergency lighting.
                          Position/Status        Valves locked open/closed
                          Status Indication      F&G system, ESD valve status, fire damper status, alarm status
                          Reliability (or PFD)   ESD/PSD system, Fire & Gas system and components
                          Availability           ESD/PSD system, Fire & Gas system and components
                          Distribution/Coverage   Detectors, firewater, emergency lighting, PA system and beacons
                          Redundancy             Separate PA systems, UPS, voted sensors, valve actuation
                          Segregation            Dual  UPS  supply  cabling,  dual  PA  system  cabling  and  PA  amplifier
                                                 racks, Emergency generator (from main generation), subsidiary control
                                                 and communication room (from CCR)
                          Accessibility and operability   Safety  equipment,  escape  routes,  triage  areas  (including  adequate
                                                 emergency lighting)
                          Resistance to Fire     ESD valves, Temporary Refuge, fire dampers, cables
                          Resistance to Explosion   See Segregation
                          Resistance to Vibration   Fire & Gas Detectors, process instrumentation, navaid lighting
                          Resistance to Dropped Objects   See Segregation
                          Resistance to Impact   Ballast control system on MODUs and FPSOs (to preserve stability)
                          Resistance to Mechanical Damage   Protection  of  cables,  valve  hydraulic/pneumatic  vent  lines,  cable
                                                 armouring.
                          Protection against Upset Conditions  Provision and set-points of piping system instrumentation
                          Compatibility          Electromagnetic Compatibility
                          Corrosion Protection   Impressed current cathodic protection
                          Prevent potentially unsafe mode of   Ballast control system, power management system, process monitoring
                          operation              and control system(s)

                         FIGURE 9.2.2
                         Checklist of Parameters to be considered for performance standards relating to electrical
                         equipment and instrumentation. ESD, emergency shutdown; FPSO, floating production,
                         storage and offloading; HVAC, heating, ventilation and air conditioning; MODU, mobile
                         offshore drilling unit; PA, public address; PFD, probability of failure on demand; PSD,
                         process shutdown; UPS, uninterruptible power supply.