Page 292 - Orlicky's Material Requirements Planning
P. 292

CHAPTER 14      System Effectiveness: A Function of Design and Use              271


           FIGURE 14-8
                                                               Week
           Solution of
           problem of                               28  29  30  31  32  33  34  35
           coverage.
                                Gross Requirements  3   7  10  6   8  10  14  10  Fabricated
                                                                                  Part X
                                Scheduled Receipts
                                On Hand         38  35  28  18  12  4  –6 –20 –30
                                Planned-Order Releases         20     25

                                                    Firm
                                                    Planned
                                                    Order


                                Gross Requirements             20     25
                                                                                  Raw
                                                                                  Material Y
                                Scheduled Receipts         15
                                On Hand          5  5   5  20  0   0  –25 –25 –25
                                Planned-Order Releases  25


        ning, the two records appear as in Figure 14-8. The problem is solved, and an order for
        25 units of item Y will be released under normal lead time. Note that because the planned
        order for item X has been reduced, the MRP system has compensated by moving the next
        planned order in the parent record forward. In the real situation, the quantity of the sec-
        ond planned order (recomputed under LTC) also might be affected.
             The preceding example illustrates a problem of coverage caused by an increase in
        component-item gross requirements, but the same type of problem would have arisen if
        the vendor of the open order for 15 had indicated that it was unable to ship on time. If
        item Y were a fabricated part, the scrapping of 10 of the 15 in process would have the
        same effect. In our example, the inventory planner was able to reduce the parent planned
        order because lot sizing covered multiple periods’ net requirements. Had the planned
        order covered a single period, it still could have been reduced by an amount within its
        scrap allowance or other excess over the quantity of the net requirement. Safety stock at
        the parent level also would allow a reduction in the planned order.
             The type of problem illustrated in the preceding examples sometimes can be solved
        without having to reduce the quantity of the parent planned order; instead, only its tim-
        ing is changed. If the parent item’s planned lead time can be compressed (as it often can—
        see discussion of lead-time flexibility in Chapters 7 and 12), the respective planned-order
        release can be rescheduled for a later period and held in place as a firm planned order.
             Rescheduling a parent planned-order release consequently (after the next explosion)
        will reschedule the corresponding component gross requirement and thus solve the prob-
        lem of net requirements coverage. In Figure 14-7, for example, if the lead time of parent
        item X were reduced by one week (for purposes of the first planned-order release only),
   287   288   289   290   291   292   293   294   295   296   297