272                                                 PART 3      Managing with the MRP System


        it would result in the net requirement for component item Y occurring one week later.
        This would alleviate the problem of net requirements coverage by allowing an extra week
        for procurement of the material.
             If the inventory planner is unable to solve a problem of coverage by pegging to the
        next-higher level and manipulating planned-order or open-order data, he or she may peg
        from the parent record to its parent records in an attempt to find a solution. Successive
        pegs may lead to the MPS, which may have to be changed to solve a particular compo-
        nent-item problem.