Page 472 - Orlicky's Material Requirements Planning
P. 472

450                                                 PART 4      Looking Backward and Forward



                        FIGURE 26-20
                        Staggered schedule with critical ASRLT orders identified.

                                                                           SAW
                                                                                    SAC

                                                                         SAY         SAE        End Item
                                                                 SAA
                                                                                                Due
                                                                                SAD     SAF
                                                                    SAB                         Date
                                                                                           FPZ
                                                                                 SAZ
                                                                                      SAX


                       0    10    20   30    40    50   60    70   80    90   100   110  120   130   140
                                                         PPE
                                                                        PPD              PPA
                                                                  PPI
                                                             PPF
                       PPH               PPG                              PPK

                                                                            PPB
                                                           PPC
                                                                         PPJ                                Downloaded by [ Singapore Polytechnic Library 176.79.113.174] at [06/05/21]. Copyright © McGraw-Hill Global Education Holdings, LLC. Not to be redistributed or modified in any way without permission.




                        FIGURE 26-21

                        Example planning screen for Part FPZ.
                           Order                   Request  Promise
                       Part  Number  Profile Start Date  ASRLT  Date  Date  Late Quantity  Vendor  Customer Source
                       PPH  PO-000591  LTM  2/15  75  2/28  2/28     1   SpaceTech    Driven by WO-000589, SAA
                       PPG  PO-000590  LTM  1/19  40  2/28  2/28     1   Siemens      Driven by WO-000589, SAA
                       PPE  PO-000592  LTM  2/13  20  3/05  3/05     1   Sony         Driven by WO-000587, SAB
                       PPF  PO-000593  LTM  2/18  15  3/05  3/05     1   SpaceTech    Driven by WO-000587, SAB
                       PPC  PO-000594  LTM  2/18  25  3/15  3/15     1   Boeing       Driven by WO-000582, SAY
                       SAA  WO-000589  NB  2/28  80  3/05  3/05      1                Driven by WO-000587, SAB
                       PPI  PO-000596  LTM  3/03  25  3/28  3/28     1   Raytheon     Driven by WO-000588, SAZ
                       SAB  WO-000587  NB  3/05  90  3/15  3/15      1                Driven by WO-000585, SAW
                       PPD  PO-000595  LTM  3/09  18  3/27  3/27     1   MicroTech    Driven by WO-000583, SAD
                       PPJ  PO-000598  LTM  3/15  20  4/04  4/04     1   SpaceTech    Driven by WO-000586, SAC
                       SAY  WO-000582  NB  3/15  45  4/04  4/04      1                Driven by WO-000580, SAE
                       SAW  WO-000582  NB  3/15  102  3/27  3/27     1                Driven by WO-000583, SAD
                       PPK  PO-000599  LTM  3/18  20  4/07  4/07     1   Siemens      Driven by WO-000584, SAX
                       PPB  PO-000597  LTM  3/20  15  4/04  4/04     1   Sony         Driven by WO-000580, SAE
                       SAD  WO-000583  NB  3/27  117  4/11  4/11     1                Driven by WO-000581, SAF
                       SAZ  WO-000588  NB  3/28  32  4/04  4/04      1                Driven by WO-000586, SAC
                       SAE  WO-000580  NB  4/04  58  4/17  4/17      1                Driven by WO-000579, FPA
                       SAC  WO-000586  NB  4/04  35  4/07  4/07      1                Driven by WO-000584, SAX
                       SAX  WO-000584  NB  4/07  39  4/11  4/11      1                Driven by WO-000581, SAF
                       SAF  WO-000581  NB  4/11  123  4/17  4/17     1                Driven by WO-000579, FPA
                       PPA  PO-000600  LTM  4/12  5  4/17  4/17      1   SpaceTech    Driven by WO-000579, FPA
                       FPZ  WO-000579  NB  4/17  136  5/01  5/01     1         NASA   Driven by Atlantis, line 1, NASA
   467   468   469   470   471   472   473   474   475   476   477