Page 473 - Orlicky's Material Requirements Planning
P. 473

CHAPTER 26      Demand-Driven Planning                                          451



                             FIGURE 26-22
                             Slippage in Part FPZ schedule.

                                Order                   Request  Promise
                            Part  Number  Profile Start Date  ASRLT  Date  Date  Late  Quantity  Vendor  Customer Source
                            PPH  PO-000591  LTM  2/15  75  2/28  2/28     1   SpaceTech    Driven by WO-000589, SAA
                            PPG  PO-000590  LTM  1/19  40  2/28  2/28  2 Days  1  Siemens  Driven by WO-000589, SAA
                            PPE  PO-000592  LTM  2/13  20  3/05  3/05     1   Sony         Driven by WO-000587, SAB
                            PPF  PO-000593  LTM  2/18  15  3/05  3/05     1   SpaceTech    Driven by WO-000587, SAB
                            PPC  PO-000594  LTM  2/18  25  3/15  3/15     1   Boeing       Driven by WO-000582, SAY
                            SAA  WO-000589  NB  2/28  80  3/05  3/05  2 Days  1            Driven by WO-000587, SAB
                            PPI  PO-000596  LTM  3/03  25  3/28  3/28     1   Raytheon     Driven by WO-000588, SAZ
                            SAB  WO-000587  NB  3/05  90  3/15  3/15  2 Days  1            Driven by WO-000585, SAW
                            PPD  PO-000595  LTM  3/09  18  3/27  3/27     1   MicroTech    Driven by WO-000583, SAD
                            PPJ  PO-000598  LTM  3/15  20  4/04  4/04     1   SpaceTech    Driven by WO-000586, SAC
                            SAY  WO-000582  NB  3/15  45  4/04  4/04      1                Driven by WO-000580, SAE
                            SAW  WO-000582  NB  3/15  102  3/27  3/27  2 Days   1          Driven by WO-000583, SAD
                            PPK  PO-000599  LTM  3/18  20  4/07  4/07     1   Siemens      Driven by WO-000584, SAX
                            PPB  PO-000597  LTM  3/20  15  4/04  4/04     1   Sony         Driven by WO-000580, SAE
                            SAD  WO-000583  NB  3/27  117  4/11  4/11  2 Days  1           Driven by WO-000581, SAF
                            SAZ  WO-000588  NB  3/28  32  4/04  4/04      1                Driven by WO-000586, SAC
                            SAE  WO-000580  NB  4/04  58  4/17  4/17      1                Driven by WO-000579, FPA
                            SAC  WO-000586  NB  4/04  35  4/07  4/07      1                Driven by WO-000584, SAX
                            SAX  WO-000584  NB  4/07  39  4/11  4/11      1                Driven by WO-000581, SAF
                            SAF  WO-000581  NB  4/11  123  4/17  4/17  2 Days  1           Driven by WO-000579, FPA
                            PPA  PO-000600  LTM  4/12  5  4/17  4/17      1   SpaceTech    Driven by WO-000579, FPA
                            FPZ  WO-000579  NB  4/17  136  5/01  5/01  2 Days  1    NASA   Driven by Atlantis, line 1, NASA

                          example of slippage occurring within the ASRLT chain. The promise date of PPG has      Downloaded by [ Singapore Polytechnic Library 176.79.113.174] at [06/05/21]. Copyright © McGraw-Hill Global Education Holdings, LLC. Not to be redistributed or modified in any way without permission.
                          been moved back two days. It is two days late. This will result in a delay to SAA. SAA
                          lies on the ASRLT chain. The two-day delay of PPG transfers variability from a noncriti-
                          cal path to a critical path and is pushing the promise date of the end item by two days.
                               Coding feeding paths into that chain with an LTM designation is one way to gain
                          better visibility and protection for the ASRLT chain. In many cases, the LTM designation
                          itself will not prevent slides of those feeding legs from affecting the ASRLT chain, but the
                          LTM designation notifies the planner about the slide sooner. There is value in this knowl-
                          edge in order to allow the development of another tactic that will absorb the variation in
                          BOM legs that affect the ASRLT chain.
                               Figure 26-23 displays the total length of all legs in the BOM by a large number at the
                          left termination of the leg. The ASRLT is represented by the shaded boxes and remains
                          136 days. The longest non-ASRLT path is 101 days (terminating in PPG). This is a differ-
                          ence of 35 days. This leg can be started a sensible period of time ahead of the late start
                          date to account for potential delays without changing or redefining the ASRLT chain. A
                           time buffer can be employed that will absorb potential disruption from a supplier with-
                           out adding any lead time to the total assembly schedule and better protect the ASRLT. All
                           activity/legs feeding into the ASRLT chain that are not part of that chain can be buffered
                           with time. Figure 26-24 is FPZ’s BOM with these time buffers inserted. The shaded rec-
                           tangular boxes represent the time buffers. The time buffers are an insertion into the lead
                           time of non-ASRLT legs. The length of each of those legs has been lengthened, and the
                           release or start dates for items on those paths are adjusted accordingly.
   468   469   470   471   472   473   474   475   476   477   478