Page 238 - Pipelines and Risers
P. 238

Installation Design                                                   21 1


        stresdcollapse will converge. Hence the wall-thickness requirements should be less for dense
        oil than for gas.

        12.6.3 Implication to Installation, Testing and Operation
        What are the implications of changing from a 3 medium to a 2 medium pipeline? All phases
        of  the pipeline installation, testing and operation will be affected by providing a limitation to
        the contents density and the minimum pressure. The principal issues for each phase are:

        Installation: The pipeline will need a facility to free flood during installation and cancel any
        differential pressure in this phase. Although the pipeline wall-thick-ness may be significantly
        reduced, the submerged pipe weight is still increased and the pipelay tensions can be-come
        too high for the present laybarge capacity. This phenomena is true in comparison with lines
        installed dry in shallow water but not deepwater.

        Testing: The pipeline internal pressure must stay above a design minimum, so although the
        pressure testing will be unaffected the drying the pipeline with ambient pressure hot air and/or
        vacuum  drying  will  not  be  possible.  Pre-commissioning would  have  to  employ  methanol
        slugs or similar followed by the product at operational pressure.

        Operation:  Throughout  the  production  life,  a  minimum  operating  pressure  must  be
        maintained otherwise the pipeline  will collapse. In  practice this  would require  a  minimum
        pressure  assurance  system,  such  as having  isolation  valves,  which  would  prevented  the
        pipeline pressure dropping below a specified minimum.


        The  implications  for  both  the  testing  and  operation  phases,  although  significant,  are  not
        insurmountable  with  existing  technology and  practices.  On  the  other  hand,  the  impact  on
        installation is significant and is what this section will focus on.

        12.6.4 Installing Free Flooding Pipelines
        Installing pipelines dry has been logically adopted as the lay tensions can be kept relatively
        low and there is a large margin to be gained between  with the increased submerged weight
        during operation (for stability purposes). This logic is sound in shallow water but can not be
        extrapolated to depths in excess of  1000m. The required wall-thickness of an airfilled pipeline
        becomes so large that the associated submerged weight will require lay tensions significantly
        greater than present lay barge capacity.

        To illustrate this phenomenon Figure  12.27 and  12.28 illustrates the required pipeline wall-
        thickness for a range of pipeline diameters. For the purposes of comparison it is assumed the
        pipeline would be carrying oil at a density of  800 kg/m3 at a pressure of  200 barg. Figure
        12.27 illustrates  the  wall-thickness for  a pipeline  installed  while  empty  and  Figure  12.28
        illustrates the associated wall-thickness when the pipeline is installed flooded.
   233   234   235   236   237   238   239   240   241   242   243