Page 99 - Plant design and economics for chemical engineers
P. 99

GENERAL DESIGN CONSIDERATIONS  77
     design-related functions, such as capital-cost estimating, process and equipment
     design, and plant layout. It is particularly important to learn what is legally
     required by the Environmental Protection Agency (EPA), the Occupational
     Safety and Health Administration (OSI-IA),  and corresponding regulatory groups
     at the state and local levels. As a minimum, every design engineer should
     understand how the federal regulatory system issues and updates its standards.
         Every design engineer must be certain that a standard being used has not
     been revised or deleted. To be sure that a regulation is up-to-date, it must first
     be located in the most recent edition of the  Code of Federal Regulations (CFR).
     Next, the Cumulative Lkt of CFR Sections Affected must be checked to see if
     actions have been taken since the CFR was published. If action has been taken,
     the Cumulative List will indicate where the changes can be found in the Federal
    Register.  The latter provides the latest regulations and legal notices issued by
     various federal agencies.


     Environmental   Regulations
     Several key aspects of the U.S. Federal environmental regulation as spelled out
     in legislation entitled Protection of the Environment  (Title 40, Chapter 1 of the
     CFR)  are listed in Table 7. This checklist must also consider applicable state
     and local codes. Often these may be more stringent than the federal codes or
     may single out and regulate specific industries.
         Note that Part 6 of Title 40, Chapter 1, in Table 7 requires the prepara-
    tion of an Environmental Impact Statement (EIS). The National Environment
    Policy Act (NEPA)  requires that federal agencies prepare such a statement in
     advance of any major “action” that may significantly alter the quality of the
    environment. To prepare the EIS, the federal agencies require the preparation
    of an Environmental Impact Assessment (EIA).  The latter is required to be a
    full-disclosure statement. This includes project parameters that will have a
    positive environmental effect, negative impact, or no impact whatsoever. Gener-
    ally, design engineers will only be involved with a small portion of the EIA
    preparation, in accordance with their expertise. However, each individual should
    be aware of the total scope of work necessary to prepare the EIA as well as the
    division of work. This will minimize costly duplication, as well as provide the
    opportunity for developing feasible design alternatives.
         The preparation of an Environmental Impact Assessment requires deter-
    mining what environmental standards require compliance by the project, obtain-
    ing baseline data, examining existing data to determine environmental safety of
    the project, preparing an effluent and emission summary with possible alterna-
    tives to meet acceptable standards, and finally preparing the environmental
    statement or report. Since it may require a full year to obtain baseline data such
     as air quality, water quality, ambient noise levels, ecological studies, and social
     surveys, emissions and effluents, studies should take place concurrently to avoid
     delay in preparing the EIA. The emissions and effluents studies must include all
    “significant” sources of pollution. Omission of data could cause inconsistencies
   94   95   96   97   98   99   100   101   102   103   104