Page 341 - Practical Power System and Protective Relays Commissioning
P. 341

336  Practical Power System and Protective Relays Commissioning



























            FIGURE 20.3.3 Relay power swing characteristic.

               The results in Table 20.3.3 should be verified as per the injected values
            to the relay.



              TABLE 20.3.3 Relay Test Sheet 2
              Injected Impedance       Relay Action  Remarks
              Z pass between Z ps and Z 3  Trip  Yes  Trip based on fault location
              characteristic very fast              with Z 1 or Z 2 or Z 3 as injected
                                       Block  No
                                                    fault
                                       Trip   No
              Z pass between Z ps                   Block Z 1 and Z 2 and Z 3
              characteristic and Z 3   Block  Yes   operation after 5 s
              characteristic very slow



            7. Switch on to fault instantaneous high-speed OC function test
               During this test we will stop operation of the distance function to be
            switched off and also backup OC function to be switched off.
               We simulate this fault as a three-phase fault-close up to the relay location
            for Example, closing of Transmission Line (TL) on a movable earth cables
            put on three phases of the TL for maintenance purposes but forgotten on the
            line after maintenance procedures are finished.
               I pickup for Switch on to fault (SOTF) 5 0.1 A . 5% I N
               As I N 5 1A
   336   337   338   339   340   341   342   343   344   345   346