Page 344 - Practical Power System and Protective Relays Commissioning
P. 344

Protective Relays Testing and Commissioning Chapter | 20  339


             Subchapter 20.4


             Line Differential Protection Testing and
             Commissioning


             20.4.1 OLD-TYPE PILOT WIRE DIFFERENTIAL PROTECTION
             TESTING

             As shown in Fig. 20.4.1 for simple pilot wire differential protection, this sys-
             tem has a summation CT convert 3ɸ values from CTs to a single-phase
             quantity to be transferred to the other end by a pilot wire.
             1. Secondary insulation resistance test
                   By disconnecting the pilot wire from both sides of the relays the insu-
                lation between the pilot wire and earth for each wire is measured.
             2. Pilot loop resistance tests
                   The pilot wires are disconnected at both sides of the line and shorted
                at one side, then the resistance of the pilot in the other side of the line is
                measured, including the values of padding resistors and without padding
                resistors.
             3. Pilot connection checks
                   Check that the insulation transformer isolates the pilot at the two ends
                of the line. This transformers are used as isolation transformers and are
                very important for the safety of persons working on the relay.
             4. Secondary Injection Tests
                4.1 Operation and Tripping Current Values Secondary Injection Test
                Open the CT links and trip links and inject the current between the phase
             and neutral to the relay and increase the injected current until the relay




















             FIGURE 20.4.1 Simple pilot wire differential protection.
   339   340   341   342   343   344   345   346   347   348   349